Projects & Initiatives

Every significant city project and initiative followed over time: construction projects with their contracts, pay applications and change orders, and the plans, programs, agreements, developments and policies the council worked on. Open one for its timeline, who was involved, costs, votes, changes and documents.
Compiled from published City of Tiffin documents (agendas, minutes, resolutions, memos, pay applications and payables lists); not official accounting or an official project record. Every event links to the page it was read from. Amounts marked "as printed" are the city's own figures; totals from the payables lists are a lower bound where a list did not reconcile or where the lists in the archive do not reach back (they begin in 2021).
45projects and initiatives (phases inside their parents)
3design
15ongoing
6under construction
Original contracts vs change orders, city-wide

Park Place City Center

Development or agreementOngoing
2016–2026
Last activity 2026-10-14 · 191 events

Water Treatment Plant Upgrades

Capital projectUnder construction
2022–2026$12.2M
Last activity 2026-10-06 · 74 events

Tiffin Fire Department

Program or serviceOngoing
2007–2026$919k
Last activity 2026-10-06 · 96 events

Tiffin Community Recreation Center

Capital projectUnder construction
2016–2026$11.4M
Last activity 2026-10-06 · 76 events

Roberts Ferry Road & Village Drive Traffic Signal

Capital projectUnder construction
2025–2026$368k
Last activity 2026-10-06 · 7 events

Original Town Urbanization

Capital projectUnder construction
2017–2026$5.61M
Last activity 2026-10-06 · 9 events

North Park Road Improvements (STP-U-7662(615)--70-52)

Capital projectUnder construction
2019–2026$5.59M
Last activity 2026-10-06 · 93 events

Well #6

Capital projectDesign
2026$1.24M
Last activity 2026-09-15 · 3 events

Urban renewal areas and TIF

Program or serviceOngoing
2010–2026
Last activity 2026-09-15 · 178 events

Local option sales tax (2023 special election)

PolicyComplete
2022–2026
Last activity 2026-09-15 · 6 events

US Highway 6 Reconstruction

Capital projectDesign
2025–2026$756k
Last activity 2026-09-01 · 18 events

Trails and sidewalks

InfrastructureOngoing
2011–2026$423k
Last activity 2026-08-18 · 18 events

Andersen Addition

Development or agreementOngoing
2018–2026
Last activity 2026-08-18 · 58 events

Forevergreen Road Earth Stockpile / Grading

Capital projectUnder construction
2025–2026$153k
Last activity 2026-07-07 · 16 events

Broadband and cable (South Slope, Mediacom, Kinetic)

Development or agreementOngoing
2004–2026
Last activity 2026-06-02 · 5 events

Tiffin Heights

Development or agreementOngoing
2013–2026$884k
Last activity 2026-05-19 · 75 events

City parks and recreation facilities

FacilityOngoing
2010–2026$303k
Last activity 2026-05-19 · 55 events

80/380 Commerce Park (Village Drive)

Development or agreementOngoing
2017–2026
Last activity 2026-04-07 · 26 events

Prairie Village / Prairie West

Development or agreementOngoing
2013–2026
Last activity 2026-03-17 · 150 events

Grove Park

Development or agreementOngoing
2018–2026
Last activity 2026-03-03 · 34 events

Law enforcement contract with the Johnson County Sheriff

Program or serviceOngoing
1974–2026$1.98M
Last activity 2026-02-17 · 110 events

Joint projects with the Clear Creek Amana school district

Development or agreementOngoing
2000–2026
Last activity 2026-02-04 · 51 events

Well #5 (test well, pump, controls and water main)

Capital projectComplete
2021–2025$336k
Last activity 2025-04-01 · 71 events

Jasper Avenue / Forevergreen Road Roundabout (28E agreement)

InfrastructureDesign
2021–2025
Last activity 2025-01-21 · 5 events

Kimberlite Street – South Improvements

Capital projectComplete
2024$292k
Last activity 2024-11-05 · 29 events

Springmier Community Library

Program or serviceOngoing
1977–2026
Last activity 2024-09-03 · 30 events

Comprehensive Plan

Plan or studyComplete
2013–2024
Last activity 2024-08-06 · 12 events

Potter Creek Interceptor Sewer

Capital projectComplete
2021–2024$1.08M
Last activity 2024-07-02 · 31 events

Zoning and subdivision code amendments

PolicyOngoing
2012–2023
Last activity 2023-12-05 · 92 events

Woodfield Ridge

Development or agreementUnknown
2007–2023
Last activity 2023-10-17 · 27 events

Public Works Building

Capital projectComplete
2021–2023$2.58M
Last activity 2023-08-08 · 53 events

Permeable Paver Parking Project

Capital projectComplete
2020–2022$387k
Last activity 2022-06-07 · 30 events

Tiffin Roundabout (Park Road / Highway 6, STP-A-006-7(90)--22-52)

Capital projectComplete
2019–2022$3.26M
Last activity 2022-05-03 · 34 events

Roberts Ferry Road Reconstruction

Capital projectComplete
2018–2021$1.46M
Last activity 2021-07-20 · 33 events

Roundabout Gateway Signage

Capital projectComplete
2020–2021$13k
Last activity 2021-04-06 · 8 events

Wastewater Treatment Plant Expansion – Phase Two

Capital projectComplete
2017–2021$5.80M
Last activity 2021-01-19 · 45 events

2019 Park Road Paving Project

Capital projectComplete
2019–2021
Last activity 2020-11-17 · 16 events

Traffic Signals – Ireland Avenue/Roberts Ferry Road and Highway 6/Marengo Road

Capital projectComplete
2018–2021
Last activity 2020-11-03 · 21 events

2019 Improvements – Forevergreen Road

Capital projectComplete
2018–2020
Last activity 2020-10-20 · 26 events

2019 Storm Water Rehabilitation Projects

Capital projectComplete
2019–2020
Last activity 2020-06-16 · 14 events

Deer View / Highway 6 Traffic Signalization

Capital projectUnknown
2019–2023
Last activity 2019-12-03 · 10 events

Ireland Avenue Project (south)

Capital projectUnknown
2014–2018
Last activity 2018-08-07 · 49 events

Original Town Sanitary Sewer Inflow & Infiltration Reduction

Capital projectComplete
2016–2017
Last activity 2017-05-16 · 24 events

2013 Capital Improvement Project

Capital projectComplete
2013–2015
Last activity 2015-12-09 · 8 events

Jasper Avenue Watermain Extension

Capital projectUnknown
2013–2014
Last activity 2014-06-25 · 14 events

"Cost" is the headline figure named under it: the contract sum to date from the newest pay application, else the total of the payables lines linked to it (the lists begin in 2021), else the largest award, bid or estimate printed in its documents. A parent's cost adds its phases'. "Completed vs contract" is completed and stored work over the contract sum on the newest pay application; above 100% means the final quantities ran over the contract sum. Statuses are derived from the events (a ✎ marks one set by hand, with the source on its page). JSON

Data last updated October 14, 2026. Built from the archive's documents; see how the data is built.