Shamrock Center

Jul 16, 2019 – Jan 4, 2022 · last activity January 4, 2022 · follow this project (feed)
Compiled from published City of Tiffin documents (agendas, minutes, resolutions, memos, pay applications and payables lists); not official accounting or an official project record. Every event links to the page it was read from. Amounts marked "as printed" are the city's own figures; totals from the payables lists are a lower bound where a list did not reconcile or where the lists in the archive do not reach back (they begin in 2021).

A commercial and industrial subdivision by Hightower Development, Inc.: rezoning of a portion from C-2B to M-2 (Ordinance 2019-461), preliminary plat and developer's agreement (Resolutions 2019-104, 2019-105, September 2019), final plat (Resolution 2020-053, June 2020), the June 2020 addition to the Tiffin Urban Renewal Area with a tax-increment rebate agreement (not to exceed $250,000 over five years) and the removal of the sidewalk requirement from its subdivider's agreement (Resolution 2022-002).

Status: no activity since 2022-01-04

11events on the timeline

City money

Private development with city money

The city's records show city money in this development:

Amounts printed in its records, not yet classified

  • $50,000.00 2020-07-07 · nt Motion to amend the agreement to a 5-year, not to exceed $250,000 ($50,000 per year) developme doc 3560 p.3

What was checked

  • Payables lists (2018-01-02 to 2026-10-20): 0 lines naming it, to its developer or on its own accounts.
  • TIF register (19 development agreements and rebates): 1 linked — listed below.
  • Motions, agenda items and documents linked to it (11 events, 2019-07-16 to 2022-01-04): 2 amounts printed — each classified below.
  • Budget worksheets (FY2019–FY2027): no budget line of its own.

City money in this development: Hightower Development's tax-increment rebate agreement for the Shamrock Center (Resolution 2020-058, not to exceed $250,000 over five years; TIF register).

Timeline

Each mark is an event (●), a change (◆) or a failed or tabled vote (✕), on the lane of its kind; bands above the lanes are the phases. Click a mark to find it in the list below.

Costs and funding

Cash flow

Where the money came from (funding sources as printed, the city funds the payments were booked to) and who was paid. Hover or tab to a band to follow it; click to open the fund, the payee's payments or the source page.

Loading…

    Every flow as a table

    JSON

    Who is involved

    Changes

    Votes

    Key motions on this subject with their outcome. Names come from the minutes' roll calls; when the minutes give only "all ayes", the ayes are counted from the attendance, and when they name only the nays, the ayes are the voting members present less the nays (marked *).