Capital project · Complete
2013 Capital Improvement Project
A 2013 street and utility capital improvement project: hearing and letting set in February-March 2013, plans adopted (Resolution 2013-050), change orders through 2014, and final completion and acceptance in December 2015 (Resolution 2015-134). Found by the discovery pass and curated.
Status: acceptance or closeout 2015-12-09
Timeline
Each mark is an event (●), a change (◆) or a failed or tabled vote (✕), on the lane of its kind; bands above the lanes are the phases. Click a mark to find it in the list below.
Phases
| Phase | Status | Dates | Cost |
|---|
Costs and funding
Cash flow
Where the money came from (funding sources as printed, the city funds the payments were booked to) and who was paid. Hover or tab to a band to follow it; click to open the fund, the payee's payments or the source page.
Loading…
Every flow as a table
Original contract vs change orders
Who is involved
Changes
Votes
Key motions on this subject with their outcome. Names come from the minutes' roll calls; when the minutes give only "all ayes", the ayes are counted from the attendance, and when they name only the nays, the ayes are the voting members present less the nays (marked *).
All events
| Date | Kind | What | Amount | Sources |
|---|
Documents and instruments
Related
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.