For the Final Acceptance of the Well #5 Improvements Project, Tiffin, Iowa – Contractor – Shawver Well Company

adopted · Aug 20, 2024

Projects: Well #5 (test well, pump, controls and water main)

Timeline

DateStepRecorded inMotion and votes
Aug 20, 2024adopted minutes
meeting 2024-08-20
document
Motion to approve Resolution No. 2024-055 – A Resolution for the Final Acceptance of the Well #5 Improvements Project, Tiffin, Iowa – Contractor – Shawver Well Company by Limkemann
moved Limkemann, seconded Orris: carried 5 ayes