contract agreement · E-3
Approval of Change Order #3 – Tricon Construction Group – Water Treatment Facility Upgrade — E-3
Page 60 of 72
Text read by the vision model; check the PDF for anything that matters.June 9, 2026
Tim Kasparek
City of Tiffin
300 Railroad Street
Tiffin, IA 52340
Project: Tiffin Water Treatment Facility Upgrade
Re: COR # 18
Truss Design Code Changes to IBC 2018/ASCE 7-16, per attached.
ReVosWel Code Changes – Calculation/Drawing Updates 1,200.00
Tricon - Carpenter (16hrs @ 78.77/hr) - MCC Room Truss Changes 1,260.32
Tricon - Carpenter (20hrs @ 78.77/hr) - RO Bldg Truss Changes 1,575.40
Tricon - Carpenter (1hr @ 78.77/hr) - Final Building Inspector Re-Review 78.77
Tricon - Material 472.94
Sub-Total 4,587.43
OHP (Subcontracted) 60.00
OHP (Self-Performed) 508.11
General Liability Insurance 92.39
Bond 77.14
Total $ 5,325.07
Approved By:
Tom Shedek ________________________________ 6/9/2026
Project Manager - Tricon Construction Date
Clint Wienen – MSA Professional Services Inc ____________ Date
City of Tiffin ________________________________ _________
Date
Sources
- revize: E-3 (DSuxr8xIE877VnS5HXwn1QE22BJNy9.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-3 Approval of Change Order #3 – Tricon Construction Group – Water Treatment Facility Upgrade
Data last updated October 17, 2026. Built from the archive's documents; see how the data is built.