Text read by the vision model; check the PDF for anything that matters.Southside Concrete PROPOSAL
Scott McAtee / 4195 Saint Catherine Road / Bellevue IA 52031
563.543.0464 / [email protected]
Submission Date: 9/24/2025
Project: Tiffin WTP BLDG 10 Quote
Project Address:
Date of Plans:
Submitted to: Item 2-4
I hereby submit specifications and estimates for:
BLDG 10 Fluoride Room Add-on from Building Inspector Changes
Concrete 1 CY @ 185.00 $ 185.00
Rebar $ 600.00
Misc Materials $ 15.00
Labor 5 MH @ 80.00 $ 400.00
15% O/P $ 180.00
TOTAL $ 1,380.00
NOT INCLUDED:
I propose to furnish material and labor - complete in accordance with the above specifications per bid documents.
Respectfully submitted: Scott L. McAtee
This proposal may be withdrawn by Southside Concrete if not accepted within 30 days from submission date above.
Any alterations/deviations from above specifications involving extra costs will be executed only upon written order and will become an extra charge over and above this estimate. All agreements contingent upon strikes, accidents, or delays beyond my control.
Acceptance of Proposal
The above prices, specifications and conditions are satisfactory and are hereby accepted. Southside is authorized to perform work as quoted. Payments will be made per bid documents.
Signature: ____________________________ Date: ____________________________
Sources
- revize: E-3 (DSuxr8xIE877VnS5HXwn1QE22BJNy9.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-3 Approval of Change Order #3 – Tricon Construction Group – Water Treatment Facility Upgrade
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.