contract agreement · E-3
Approval of Change Order #3 – Tricon Construction Group – Water Treatment Facility Upgrade — E-3
Page 20 of 72
Text read by the vision model; check the PDF for anything that matters.Tricon Construction, Inc.: Tiffin WTF Upgrades 25-23
Bill to
Tricon Construction, Inc.
Estimate details
P.O. Number: CO #3, #4, #5 1-14-26 Email
Sales Rep: Nate Schmidt
Estimate no.: 2883
Estimate date: 01/27/2026
Expiration date: 02/27/2026
<table>
<tr>
<th>#</th>
<th>Description</th>
<th>Qty</th>
<th>Rate</th>
<th>Amount</th>
</tr>
<tr>
<td>1.</td>
<td>Material and labor to complete masonry related changes per request by Tricon Construction and MSA. Revised request per email and attached documents by MSA, dated 1-21-26 from Tom Shedek to Nate Schmidt.</td>
<td></td>
<td></td>
<td></td>
</tr>
<tr>
<td>2.</td>
<td>CO #3 - 4" CMU courses added at Chlorine Room, Caustic Soda Room and Anti Scalant Room. Rebar, epoxy and grout 48" o.c.<br>Add to Base Bid:</td>
<td></td>
<td>$8,445.00</td>
<td>$8,445.00</td>
</tr>
<tr>
<td>3.</td>
<td>CO #4 - 4" CMU courses added at Chlorine Room, Caustic Soda Room and Anti Scalant Room. No rebar, epoxy and grout.<br>Add to Base Bid:</td>
<td></td>
<td>$7,472.00</td>
<td>$7,472.00</td>
</tr>
<tr>
<td>4.</td>
<td>CO #5 - Remove 1 8" CMU course from base bid heights at all RO building walls.</td>
<td></td>
<td>-$2,044.00</td>
<td>-$2,044.00</td>
</tr>
<tr>
<th colspan="4">Total</th>
<th>$13,873.00</th>
</tr>
<tr>
<td colspan="4">Expiry date</td>
<td>02/27/2026</td>
</tr>
</table>
Accepted date Accepted by CO Total: $6,401.00
Sources
- revize: E-3 (DSuxr8xIE877VnS5HXwn1QE22BJNy9.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-3 Approval of Change Order #3 – Tricon Construction Group – Water Treatment Facility Upgrade
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.