contract agreement · E-3
Approval of Change Order #3 – Tricon Construction Group – Water Treatment Facility Upgrade — E-3
Page 2 of 72
Text from the PDF text layer; check the PDF for anything that matters. CHANGE ORDER NO.: 3
Owner: City of Tiffin Owner’s Project No.:
Engineer: MSA Professional Services Engineer’s Project No.: 13603021
Contractor: Tricon Construction Group Contractor’s Project No.: 25-012-IA
Project: Tiffin WTF Upgrade
Contract Name: 13603021 – Tiffin WTF Upgrade
Date Issued: August 19, 2026 Effective Date of Change Order: September 1, 2026
The Contract is modified as follows upon execution of this Change Order:
Description: This change order shall incorporate the following changes:
Increase to switch door and frame for fluoride to room from hollow metal to FRP = $3,925.55
Increase to switch door hardware items to stainless steel for chemical room doors = $9,407.74
Increase for building modifications related to fire ratings = $15,493.29
Increase to install (2) light fixtures in the FD Aerator vault = $2,685.84
Increase to locate the split AC unit for the MCC Room to the south wall instead of the north wall
= $812.91
Increase for truss modifications to comply with IBC 2018 = $5,325.07
Attachments: Change order request documents.
Change in Contract Price Change in Contract Times
Original Contract Price: Original Contract Times:
Substantial Completion: 9/30/26
$ 12,182,553.00 Ready for final payment: 11/30/26
Increase from previously approved Change Orders No. [Increase] [Decrease] from previously approved
1 to No. 2 Change Orders No.1 to No. [Number of previous
Change Order]:
Substantial Completion: N/A
$ 20,148.91 Ready for final payment: N/A
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial Completion: 9/30/26
$ 12,202,701.91 Ready for final payment: 11/30/26
Increase this Change Order: [Increase] [Decrease] this Change Order: $0.00
Substantial Completion: 0
$ 37,650.40 Ready for final payment: 0
Contract Price incorporating this Change Order: Contract Times with all approved Change Orders:
Substantial Completion: 9/30/26
$ 12,240,352.31 Ready for final payment: 11/30/26
EJCDC® C-941, Change Order EJCDC® C-941, Change Order, Rev.1.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies
and American Society of Civil Engineers. All rights reserved.
Page 1 of 2
Sources
- revize: E-3 (DSuxr8xIE877VnS5HXwn1QE22BJNy9.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-3 Approval of Change Order #3 – Tricon Construction Group – Water Treatment Facility Upgrade
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.