contract agreement · E-3
Approval of Change Order #3 – Tricon Construction Group – Water Treatment Facility Upgrade — E-3
Page 1 of 72
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # E-3
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: August 27, 2026
AGENDA ITEM: Approval of Change Order #3 – Tricon Construction Group – Water
Treatment Facility Upgrade
ACTION: Motion
Background
The City of Tiffin entered into a construction contract with Tricon Construction Group for the
Tiffin Water Treatment Facility Upgrade. The original contract amount was $12,182,553.00.
Previously approved Change Orders No. 1 and No. 2 increased the contract by a combined
$20,148.91, bringing the contract amount to $12,202,701.91 prior to Change Order No. 3.
Change Order No. 3 incorporates several modifications identified during the construction and
review process. The changes are intended to address material selections, building and fire-rating
requirements, lighting, mechanical equipment location, and structural requirements associated
with the project. The Change Order was issued August 19, 2026, with an effective date of
September 1, 2026.
The supporting documentation includes contractor change order requests, material information,
revised plans, and related documentation. The building modifications included under this Change
Order are associated with building inspection and code-related requirements. The project plans
identify the applicable building and fire codes, including the 2018 International Building Code
(IBC) and 2024 International Fire Code (IFC).
The project documentation also indicates that the design was revised to provide 1-hour rated fire
wall assemblies for the three required control areas within the Main RO Building.
There is no change to the project schedule associated with Change Order No. 3. Substantial
completion remains September 30, 2026, and the date for readiness for final payment remains
November 30, 2026.
Recommendation
Staff recommends approval of Change Order No. 3 with Tricon Construction Group for the
Tiffin Water Treatment Facility Upgrade in the amount of $37,650.40, resulting in a revised
contract amount of $12,240,352.31. There is no change to the contract completion dates.
ATTACHMENTS: Change Order
1
Sources
- revize: E-3 (DSuxr8xIE877VnS5HXwn1QE22BJNy9.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: E-3 Approval of Change Order #3 – Tricon Construction Group – Water Treatment Facility Upgrade
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.