staff report memo · L-3
Tiffin Recreation Center – Project Update
Page 15 of 18
Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 2/06/2026
Miron Construction Co., Inc. Data Date: 06-Feb-26
Page 2 of 4
250120-35PM 20260206
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2026
Dur Dur
Feb Mar Apr May Jun Jul Aug Sep Oct Nov
2440 TSF 2380 2450 Steel - Sequence 4 Joist/Detailing 10 5 03-Feb-26 A 13-Feb-26
2460 TSF 2390 2470 Steel - Sequence 5 Beams/Channels 9 9 09-Feb-26 19-Feb-26
2450 TSF 2440 2390, Steel - Sequence 4 Metal Decking 4 4 10-Feb-26 13-Feb-26
1430
3130 MERIT 3120, 3200 Roofing Building C 6 6 12-Feb-26 19-Feb-26
3110,
2390 TSF A1120
2310, 2460 Steel - Sequence 5 Track Rods 2 2 16-Feb-26 17-Feb-26
2450,
2470 TSF 2370
2460 2480 Steel - Sequence 5 Detailing 4 4 16-Feb-26 19-Feb-26
2480 TSF 2470 2400, Steel - Sequence 5 Decking 4 4 20-Feb-26 25-Feb-26
2950
3200 MERIT 3130, 2850, Exterior Metal Panels Building C 2 2 20-Feb-26 23-Feb-26
3110, 2780
2400 TSF A1110,
2480, 2410 Steel - Sequence 6 Main Stair Install/Detail 5 5 26-Feb-26 04-Mar-26
2320
2110 AAAMECH 1440 1990 Plumbing Inwall Rough In - Exterior PEMB Walls 10 10 03-Mar-26 16-Mar-26
2780 GENTRADES 3200, 1430, Temp Heat 3 3 03-Mar-26 05-Mar-26
1450, 1390
2850 ILTENS 1440,
1440, 2430 RTU Setting 2 2 03-Mar-26 04-Mar-26
3190,
3140 PRICEELEC 3200,
1440 1990 Electrical Inwall Rough In - Exterior PEMB Walls 10 10 03-Mar-26 16-Mar-26
1430 MIRON CONC 2450, 1550, Prep/Pour/Strip 2nd Floor to GL 5 5 5 06-Mar-26 12-Mar-26
2780 1570,
2430 TSF 2850, 1840,
1960 Steel - Sequence 9 Mechanical Screens Install 15 15 12-Mar-26 01-Apr-26
2350
1410 MIRON 1390 Preinstall - Gym Floor and Slab on Grade 0 0 13-Mar-26
2950 MIRON CONC 1430, 1980 Prep/Pour/Strip 2nd Floor Sequence 2A 3 3 13-Mar-26 17-Mar-26
2480
1980 MIRON CONC 2950 1390, Prep/Pour/Strip 2nd Floor Sequence 2B 2 2 18-Mar-26 19-Mar-26
2930
1390 MIRON CONC 1450, 1970, Prep/Pour/Strip Slab on Grade - Gym Floor (Orange) 5 5 20-Mar-26 26-Mar-26
2780, 1360,
1550 PEARSON 1980,
1430, 1580,
2340, 2nd Floor Interior Steel Stud Framing 5 5 20-Mar-26 26-Mar-26
2980 1560,
1570 AAAMECH 1430 3160
1560, 2nd Floor Overhead Rough In - MEP 8 8 20-Mar-26 31-Mar-26
1580
2930 TRI CITY FP 1980 1680 2nd Floor Fire Protection 15 15 20-Mar-26 09-Apr-26
1970 MIRON 1390 1720 Gym Floor Moisture Mitigation 40 40 27-Mar-26 21-May-26
1360 MIRON CONC 1390 2840, Prep/Pour/Strip Slab on Grade - Pink 3 3 27-Mar-26 31-Mar-26
1520,
3160 PRICEELEC 1550 1540
1660 2nd Floor In Wall Rough In - Electrical 5 5 27-Mar-26 02-Apr-26
3170 PRICEELEC 1390 1680 Gym Area Overhead Rough In - Electrical 15 15 27-Mar-26 16-Apr-26
3180 ILTENS 1390 1680 Gym Area Overhead Rough In - Mechanical 10 10 27-Mar-26 09-Apr-26
2420 TSF 2410, 1680 Steel - Sequence 8 Running Track Railing Instal 7 7 31-Mar-26 09-Apr-26
2340
1560 AAAMECH 1550, 1660 2nd Floor In Wall Rough In - Plumbing 5 5 01-Apr-26 07-Apr-26
1570
1580 AAAMECH 1570, 1680 Gym Area Overhead Rough In - Plumbing 5 5 01-Apr-26 07-Apr-26
1390
2840 MIRON CONC 1360 2830, Prep/Pour/Strip Slab on Grade - Green 3 3 01-Apr-26 03-Apr-26
2940
2830 MIRON CONC 2840 1990, Prep/Pour/Strip Slab on Grade - Brown 3 3 06-Apr-26 08-Apr-26
2410
Actual Work
Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other
Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your
agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: Report (aV7ID4jnriuv8j8TOkLQfkg4NyNGX9.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-3 Tiffin Recreation Center – Project Update
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.