staff report memo · L-3
Tiffin Recreation Center – Project Update
Page 14 of 18
Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 2/06/2026
Miron Construction Co., Inc. Data Date: 06-Feb-26
Page 1 of 4
250120-35PM 20260206
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2026
Dur Dur
Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Tiffin Community Recreation Center 276 194 30-Sep-25 A 10-Nov-26
PRECONSTRUCTION 0 0
PRECONSTRUCTION - BP1 0 0
PRECONSTRUCTION - BP2 0 0
SUBMITTALS 10 10 09-Feb-26 20-Feb-26
A1150 GENTRADES A1030 A1080 Casework Resubmittal 10 10 09-Feb-26 20-Feb-26
A/E REVIEW / APPROVAL 10 10 23-Feb-26 06-Mar-26
A1080 GENTRADES A1150 3100 Casework Resubmittal - Reveiw 10 10 23-Feb-26 06-Mar-26
FAB / DELIVER 166 84 30-Sep-25 A 05-Jun-26
2980 MIRON DOOR 2970 2340, Hollow Metal Frames Fab and Deliver 45 25 30-Sep-25 A 13-Mar-26
1520,
2990 MIRON DOOR 2970 1550
2920 Hollow Metal Doors Fab and Deliver 60 40 30-Sep-25 A 03-Apr-26
2330 TSF 2250 2410 Steel - Sequence 7 Running Track Stair Fab and Deliver 111 20 20-Oct-25 A 06-Mar-26
2340 TSF 2260 2420 Steel - Sequence 8 Running Track Railing Fab and Deliver 107 20 28-Oct-25 A 06-Mar-26
2350 TSF 2270 2430 Steel - Sequence 9 Mechanical Screen Fab and Deliver 117 23 28-Oct-25 A 11-Mar-26
2510 ZEPHYR 3070, 1840 Curtain Wall/Aluminum Entrance/Glazing Fab and Deliver (Field 15 14 23-Jan-26 A 26-Feb-26
2500, Verif ication Openings)
2530 ZEPHYR 2520
3070, 1840 Curtain Wall/Aluminum Entrance/Glazing Fab and Deliver (Hold 45 44 23-Jan-26 A 09-Apr-26
2500 RO Openings)
3000 MIRON DOOR 2970 3080, Wood Doors & Hardware Fab and Deliver 70 64 30-Jan-26 A 07-May-26
2920
1270 OTIS 1220 1830 Elevator - Fab and Deliver 50 50 09-Feb-26 17-Apr-26
3100 GENTRADES A1030, 2080 Casework Fab and Delivery 50 50 09-Mar-26 15-May-26
A1080
3210 H2I 1390 3220 Gym Equipment Field Verification 2 2 01-Apr-26 02-Apr-26
3220 H2I 3210 2910 Gym Equipment Procurement 45 45 03-Apr-26 05-Jun-26
SITEWORK 90 90 21-May-26 28-Sep-26
2120 SCHRADER 1830 1940 Rough Grade 5 5 21-May-26 28-May-26
1940 ALL AMERICAN 1840, 1960, Site Concrete - Curbs and Sidewalks 8 8 29-May-26 09-Jun-26
2120 1950
1960 SCHRADER 1940, 1870 Final Grade 5 5 10-Jun-26 16-Jun-26
1340,
1870 CULVERS 2430
1960, 1760 Landscape 10 10 17-Jun-26 30-Jun-26
1440
1950 LLPELL 1940, 1760 Asphalt Overlay and Parking Lot Striping 5 5 22-Sep-26 28-Sep-26
1720
CONSTRUCTION 207 176 24-Dec-25 A 15-Oct-26
3190 MERIT A1090, 2850, Exterior Metal Panels Building B 4 3 24-Dec-25 A 11-Feb-26
3090 3120
1440 MERIT A1100, 2850, Exterior Metal Panels Building A 20 16 08-Jan-26 A 02-Mar-26
1370, 2110,
1450 MERIT A1110,
A1130, 1870,
1390, Roofing Building A 15 9 19-Jan-26 A 19-Feb-26
1370, 2780
2380 TSF 2370,
A1130, 2440 Steel - Sequence 4 Columns/Beams 8 1 20-Jan-26 A 09-Feb-26
2300,
2000,
Actual Work
Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other
Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your
agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: Report (aV7ID4jnriuv8j8TOkLQfkg4NyNGX9.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-3 Tiffin Recreation Center – Project Update
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.