staff report memo · L-3
Tiffin Recreation Center – Project Update
Page 16 of 18
Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 2/06/2026
Miron Construction Co., Inc. Data Date: 06-Feb-26
Page 3 of 4
250120-35PM 20260206
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2026
Dur Dur
Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1520 PEARSON 1430, 2340, 1st Floor Interior Steel Stud Framing 10 10 08-Apr-26 21-Apr-26
1360, 1530,
1540 ILTENS 2980
1300, 3150
2010, 1st Floor Overhead Rough In - Mechanical 15 15 08-Apr-26 28-Apr-26
1360 1530
2340 GENTRADES 2980, 1600, Hollow Metal Frame Installation 3 3 08-Apr-26 10-Apr-26
1550, 1660
1990 MERIT 1520
2830, 2890 PEMB - Interior Liner Panels 15 15 09-Apr-26 29-Apr-26
2110,
2410 TSF 3140
2330, 2420 Steel - Sequence 7 Running Track Stair Intall/Detail 5 5 09-Apr-26 15-Apr-26
2400,
2940 TRI CITY FP 2830
2840 1630 1st Floor Fire Protection 15 15 09-Apr-26 29-Apr-26
1840 GLAZING 1430, 1600, Glazing 15 15 10-Apr-26 30-Apr-26
2510, 1940
1530 AAAMECH 2530
1520, 1600 1st Floor In Wall Rough In - Plumbing 15 15 13-Apr-26 01-May-26
1540
1660 PEARSON 2340, 1670 2nd Floor Drywall - Hang 3 3 13-Apr-26 15-Apr-26
1560,
1670 PEARSON 3160
1660 1680 2nd Floor Drywall - Tape and Sand 5 5 16-Apr-26 22-Apr-26
3150 PRICEELEC 1520 1600 1st Floor In Wall Rough In - Electrical 15 15 22-Apr-26 12-May-26
1680 YOUNGS 1580, 1700, 2nd Floor Paint 8 8 23-Apr-26 04-May-26
1670, 2080,
3010 APPLEBY 2420,
1680 2900,
1700 2nd Floor Wall Tile 8 8 27-Apr-26 06-May-26
2010 PRICEELEC 1540, 1830 Permenant Power 1 1 29-Apr-26 29-Apr-26
1650
1830 OTIS 1270, 1740, Elevator Installation 15 15 30-Apr-26 20-May-26
2010 2120
2890 PRICEELEC 1680, 1760 2nd Floor - Electrical Trim and Lights 10 10 05-May-26 18-May-26
1990
2900 ILTENS 1680 1820 2nd Floor - Fabric Duct and Diffusers 8 8 05-May-26 14-May-26
1700 AAAMECH 1680, 2090 2nd Floor Plumbing Fixtures 5 5 07-May-26 13-May-26
3010
1600 PEARSON 2340, 1610 1st Floor Drywall - Hang 10 10 13-May-26 27-May-26
1530,
1610 PEARSON 1840,
1600 1620 1st Floor Drywall - Tape and Sand 15 15 28-May-26 17-Jun-26
2910 H2I 1680, 1720 Gym Equipment - Installation 20 20 08-Jun-26 06-Jul-26
3220
1620 YOUNGS 1610, 3080, 1st Floor Paint 8 8 18-Jun-26 29-Jun-26
1470 1630,
3020 APPLEBY 1620 1730,
1640 1st Floor Wall Tile 15 15 23-Jun-26 14-Jul-26
1630 HARGERS 1620, 1640, 1st Floor Ceiling Tile - Grid 15 15 30-Jun-26 21-Jul-26
2940 1740,
3080 MIRON DOOR 1620, 2880,
2090 Door and Hardware Installation 8 8 30-Jun-26 10-Jul-26
3000
2870 PRICEELEC 1620, 1760 1st Floor - Electrical Trim and Lig hts 10 10 08-Jul-26 21-Jul-26
1630
2880 ILTENS 1630 1820, 1st Floor - Diffusers 10 10 08-Jul-26 21-Jul-26
2090
1640 AAAMECH 1630, 1650, 1st Floor Plumbing Fixtures 5 5 15-Jul-26 21-Jul-26
3020 2090
1650 CEILING 1640 1820 1st Floor Ceiling Tile - Drop 2 2 22-Jul-26 23-Jul-26
2090 ILTENS 3080, 1720, HVAC Startup 3 3 22-Jul-26 24-Jul-26
1640, 1820,
1730 PHILLIPSFLR 1700,
1620, 1810,
1760 Flooring - Turf Area 10 10 27-Jul-26 07-Aug-26
2090
1740 APPLEBY 1630, 2080, Soft Goods Flooring - 1st Floor 10 10 27-Jul-26 07-Aug-26
1830, 2920
2090
Actual Work
Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other
Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your
agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: Report (aV7ID4jnriuv8j8TOkLQfkg4NyNGX9.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-3 Tiffin Recreation Center – Project Update
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.