staff report memo · L-3

Tiffin Recreation Center – Project Update

Dated February 17, 2026City Council — regular meeting, February 17, 2026 18 pages

Open the PDF

Page 17 of 18

Text from the PDF text layer; check the PDF for anything that matters.
Tiffin Community Recreation Center Layout Name: 250120B Construction Schedule Update 2/06/2026 Miron Construction Co., Inc. Data Date: 06-Feb-26 Page 4 of 4 250120-35PM 20260206 Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2026 Dur Dur Feb Mar Apr May Jun Jul Aug Sep Oct Nov 1810 PHILLIPSFLR 2090 1760 Athletic Flooring - 2nd Floor 15 15 27-Jul-26 14-Aug-26 2080 GENTRADES 3100, 1760 Architectural Casework Install 15 15 27-Jul-26 14-Aug-26 1620, 2860 PHILLIPSFLR 1680, 2090 1720 Athletic Flooring - 1st Floor 10 10 27-Jul-26 07-Aug-26 1720 H2I 1970, 1820, Wood Flooring - Gym Area 30 30 10-Aug-26 21-Sep-26 1620, 1950 2920 MIRON DOOR 2090, 1740, 1820 Interior Door and Harware Installation 5 5 10-Aug-26 14-Aug-26 2990, 1820 MEP 3000 1720, 1760, Test & Balance 9 9 22-Sep-26 02-Oct-26 1650, 1880 1880 MEP 2090, 1820 1760 Commissioning 9 9 05-Oct-26 15-Oct-26 WEATHER CONTINGENCY 189 189 09-Feb-26 03-Nov-26 WEATHER CONTINGENCY SITE WORK BP1 0 0 09-Feb-26 09-Feb-26 WEATHER CONTINGENCY CONSTRUCTION BP2 3 3 30-Oct-26 03-Nov-26 1890 MIRON 1770 1780 Weather Contingency Construction (Sept '25-Jan '26 12 Days) 3 3 30-Oct-26 03-Nov-26 CRITICAL 0 0 NON-CRITICAL 0 0 CONSTRUCTION BULLETINS 0 0 PROJECT COMPLETION 26 26 06-Oct-26 10-Nov-26 1760 MIRON 1820, 1770 Quality Control Review 10 10 06-Oct-26 19-Oct-26 1870, 1770 MIRON 1880, 1760 1890, Punchlist 8 8 20-Oct-26 29-Oct-26 1780 1780 MIRON 1890, 1790 Substantial Completion 0 0 03-Nov-26* 1770 1790 MIRON 1780 1800 Punchlist Corrections 5 5 04-Nov-26 10-Nov-26 1800 MIRON 1790 Final Completion 0 0 10-Nov-26 Actual Work Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.

Sources

Attached to agenda item: L-3 Tiffin Recreation Center – Project Update

This document's details as JSON

Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.