contract agreement · K-2
Discussion and Consideration to Approve a Professional Service Agreement with the Iowa DOT for the Highway 6 Improvements Project – Motion to Approve — K-2
Page 2 of 13
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-2
DOT, Division 2 funded 100% by the City of Tiffin, and Division 3 stormwater items split 94%
Iowa DOT / 6% City.
The agreement does not establish the City's final cost at $3,920,988.98. This is an estimate. The
City's actual reimbursement will be based on the quantities actually constructed, the accepted bid
prices at the time of letting, and any additional work determined to be the City's responsibility.
The Iowa DOT will bill the City approximately twice per year, with the first reimbursement
anticipated around July 1, 2027. Final billing will occur following completion of construction
and verification of the City's total project share.
Recommendation
Staff requests that the City Council approve Iowa DOT Preconstruction Agreement No. 2026-4-
131 for the U.S. 6 improvements in Tiffin and authorize the Mayor to execute the agreement on
behalf of the City.
ATTACHMENTS: Agreement
2
Sources
- revize: K-2 (Mm9BMoO5BW2h22YZFjfwxwGHtYxkLP.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-2 Discussion and Consideration to Approve a Professional Service Agreement with the Iowa...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.