K-3 - Professional Services Agreement with MSA - Water Treatment Plant
Page 5 of 11
Text read by the vision model; check the PDF for anything that matters.iv. Technical Specifications for roofing, building construction, and finishes. (Owner to make final determination on finishes.)
e. Structural
i. Structural modifications to existing water treatment plant building to accommodate breezeway construction, break room, and chlorine room
1. Assumed building materials for breezeway to be steel or wood-framed.
2. Assumed building materials for chlorine room to be wood-framed
ii. Structural design of new water treatment building, clear well and high service pump building generally following conceptual renderings.
1. Assumed building materials are precast concrete walls with metal roofing for water treatment plant addition and high service pump structures.
iii. Design of spread footing, layout, concrete and steel reinforcement for new structures including new water treatment building, high service pump building, and clear well
iv. Develop design loadings, spatial layout, and connection details for precast concrete panels and roofing.
v. Plan, Profile, and Cross Section Drawings and Details of structural construction.
vi. Technical Specifications.
f. Electrical
i. Upgrade of SCADA communication with Wells No. 3 and No. 5 including cost analysis of fiber, cellular, and radio communication alternatives (existing tower communication excluded).
ii. Generator Sizing Analysis.
iii. Electrical Service Sizing Analysis.
iv. Well No. 4 Electrolysis Investigation (30 hours estimated).
1. Goal is to assist in identifying whether an existing water treatment plant feature is contributing to electrolysis issues.
2. Results of investigation may be inconclusive or without recommendation of a solution.
3. Any well, electrical & controls modifications design is excluded from this scope of services.
v. Design of Electrical and Controls features for new water treatment plant, MCC, controls, lighting, conduit, switches, and receptacles.
vi. Drawings including details, existing and proposed one-line diagrams and P&IDs for No. Well 3, Well No. 5, EST, water treatment plant (aerator, iron filters, softeners, RO, chemical feed, HVAC, clear well and high service pumps), existing and proposed SCADA overviews.
vii. Technical Specifications.
viii. Solicit quotes directly for MCC (Motor Control Center) and controls.
1. These items have long lead times. The goal is to have the City order these items prior to bidding and then incorporate into the contract following award.
6. Permitting
MSA will submit the following permits electronically on behalf of the City, with the fees paid by the City of Tiffin: