K-3 - Professional Services Agreement with MSA - Water Treatment Plant
Page 4 of 11
Text read by the vision model; check the PDF for anything that matters.ii. Drawings including General, Details, Existing and Proposed Schematic Flow Diagram, Existing and Proposed Site Plans, Existing and Proposed Yard Piping Plan, Existing and Proposed Water Treatment Building Floor Plan and Section Views, Clear Well Plan and Section Views, Piping Plan & Profiles.
1. Existing gravity sewer is assumed to have sufficient capacity to accept filter backwash and RO concentrate from the two initial skids and no storage tank or pumping is necessary
iii. Specifications including EJCDC Project Manual, SRF Front Ends, and Technical Sections.
b. Mechanical
i. Design of process piping and equipment within the existing and proposed buildings.
ii. Identify all existing equipment scheduled for reuse, relocation, removal and/or abandonment.
1. High-service pumps to be reused/relocated from existing water treatment facility to clear well building.
iii. Design Basis Calculations and Hydraulic Analysis for water treatment system, clear well, pumps, valves, piping, chemical feed systems, and appurtenances.
1. Reverse Osmosis equipment skid drawings and details provided by manufacturer.
iv. Drawings including Removals, Process Mechanical Plan and Profile Drawings, Chemical Feed Plan and Profile Drawings.
v. Technical Specifications.
c. HVAC & Plumbing
i. Modifications to existing water treatment plant building to accommodate breezeway construction, break room, and chlorine room.
ii. HVAC Design Calculations and Analysis (for new buildings only, existing water treatment plant excluded).
iii. Plumbing Design Calculations and Analysis (for new buildings only, existing water treatment plant excluded).
1. Owner to provide water meter
iv. Drawings.
v. Specifications.
d. Architectural
i. Modifications to existing water treatment plant building to accommodate breezeway construction, break room, and chlorine room.
1. Relocation of existing office features (countertop & cabinets) to breezeway
2. Assumed building materials for breezeway to be steel or wood-framed.
3. Assumed building materials for chlorine room to be wood-framed
ii. Architectural design of new water treatment building, and high-service pump building generally following conceptual renderings.
1. Assumed building materials are precast concrete walls with metal roofing for water treatment plant addition and high service pump structures.
2. Roof, soffit, fascia, downspout, doors, and windows.
iii. Drawings for the new and existing building envelops, details of construction, and building finishes.