K-3 - Professional Services Agreement with MSA - Water Treatment Plant
Page 3 of 11
Text read by the vision model; check the PDF for anything that matters.2. Meetings
a. Client Design Meetings
i. Attend one (1) design meeting for review of 30% drawings.
ii. Attend one (1) design meeting for review of 90% drawings.
b. Council Meetings (in person)
i. Attendance of three (3) council meetings to provide project updates.
c. Internal Design Meetings
i. Internal design progress meetings with all engaged service lines (survey, civil, mechanical, electrical, plumbing, structural, architectural).
3. Data Collection
a. Topographic Survey: Collect location and elevation data of existing features at the water treatment facility for use as basis of design.
b. Base Map
i. Provide 5-foot index and 1-foot intermediate contours with labels.
ii. Locate and label all existing site features and facilities.
iii. Locate all corners of existing buildings.
iv. Locate all trees and approximate tree diameter and drip lines.
v. Locate the elevation at top and toe of all slopes and drainage areas.
c. Utility Structure Survey: Investigate utility structures to obtain field-measured invert elevations, penetrating pipe information, and condition assessment.
d. Research and locate site property lines and right of way.
e. Existing water treatment plant drawings provided by the Owner will be utilized as the basis for modifications to the existing facility. No separate interior survey or scan of the existing water plant is included in this scope of services.
4. Geotechnical Investigation Coordination
a. MSA to direct-hire Terracon as a third-party Geotechnical Consultant for soil borings and associated geotechnical report for area of proposed water treatment building and clear well for determination of ground water levels, soil characteristics, and construction recommendations.
b. MSA to stake soil boring locations and provide northing and easting to Geotechnical Consultant.
c. Geotechnical Analysis shall be included within the project Specifications as Available Project Information
5. Reverse Osmosis Treatment Facility Improvements Design
MSA will provide drawings and specifications for construction permitting of the Reverse Osmosis Water Treatment Plant as proposed within the PER and conceptual drawings attached herein. The design shall include two RO skids with future space in the building for two additional RO skids. The initial capacity of the water treatment plant will be approximately 2 MGD and the ultimate capacity of the water treatment plant will be approximately 4 MGD. The proposed 400,000-gallon clear well will be sectioned into two 200,000-gallon storage tanks to facilitate maintenance of tanks. A building will be included at the clear well location to house the high-service pumps.
a. Civil
i. Site utility modifications to support proposed water treatment features, site grading and surface restoration, driveways, sidewalks.