other

Drainage at Fire Station

Open the PDF Searchable (OCR) PDF

Page 6 of 8

Text read by the vision model; check the PDF for anything that matters.
Parking Lot Option 2: Storm Sewer Improvements 50% Reduction EST. $39,000 PRE CONSTRUCTION 20,346 SF total drainage existing to low point between doors Install intake between doors and storm system to connect to existing line POST CONSTRUCTION Water will flow into area intake and into storm sewer, there may be some ponding depending on storm level Legend: Pre-Construction Conditions Post Construction Conditions Pavement Reconstruction Existing Flow Direction Existing Gutter Outflow Location Proposed Storm Improvements

Sources

This document's details as JSON

Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.