WS - D - Staff Report - Fire Station Drainage Improvements
Page 2 of 9
Text read by the vision model; check the PDF for anything that matters.Alleyway Option 1: Partial Alleyway Replacement
52% Reduction
EST. $128,000
Pavement reconstruction with valley for surface runoff towards 2nd St
PRE CONSTRUCTION
3,760 SF total drainage existing to garage door low point
POST CONSTRUCTION
1,805 SF remains draining to garage door low point after construction
Legend:
Pre-Construction Flow Area
Post Construction Flow Area
Pavement Reconstruction
Existing Flow Direction
Existing Gutter Outflow Location
Proposed Storm Improvements
Sources