Parking Lot Option 2: Storm Sewer Improvements 50% Reduction EST. $39,000 PRE CONSTRUCTION 20,346 SF total drainage existing to low point between doors Install intake between doors and storm system to connect to existing line POST CONSTRUCTION Water will flow into area intake and into storm sewer, there may be some ponding depending on storm level Legend: Pre-Construction Conditions Post Construction Conditions Pavement Reconstruction Existing Flow Direction Existing Gutter Outflow Location Proposed Storm Improvements