In the records 1983–2026 Paid $628,380.61 Derived Named in 503 documents 20 projects
All vendors and consultants · Payments to Hart Frederick Consultants
Role on record
| Role | From | To | Source |
|---|---|---|---|
| City Engineer Mike Hart from 1983; the firm is still the city's engineering firm, engaged as needed (Eric, 2026-10-16) | 1983 (approximate) | now | document 4314, p. 6 "appoint Michael Hart as city engineer for 1990, 1990-02-08" |
| City Engineer (annual appointment) reappointed each January (2011 doc 3906 p2, 2018 doc 3643 p5, 2019 doc 3609 p5) until MSA was appointed on 2022-01-18 | 2010-01-13 | 2022-01-18 | document 3943, p. 3 "annual appointment of City Engineer to Mike Hart with Hart Frederick Consultants, 2010-01-13" |
Paid by year
| Year | Paid | Lines |
|---|---|---|
| 2018 | $80,139.85 | 1 |
| 2021 | $201,875.75 | 74 |
| 2022 | $74,070.00 | 20 |
| 2023 | $106,676.95 | 13 |
| 2024 | $115,360.56 | 15 |
| 2025 | $42,342.50 | 4 |
| 2026 | $7,915.00 | 2 |
From the payables lists the council approved (2018, and 2021 to today), May 15, 2018 – May 5, 2026.
Projects
- Original Town Urbanization – Phase Three engineer · Aug 6, 2024 – Oct 6, 2026
- Tiffin Trail – Phase 6 engineer · Oct 19, 2021 – Oct 18, 2022
- Potter Creek Interceptor Sewer engineer · Jul 20, 2021 – Jul 2, 2024
- Permeable Paver Parking Project engineer · Jun 1, 2021 – Jun 7, 2022
- Original Town Urbanization – Phase One engineer · Mar 16, 2021
- Tiffin Trail – Phase 7 engineer · Mar 16, 2021 – Sep 6, 2022
- Soccer Field Parking Lot Expansion engineer · Mar 16, 2021 – Apr 6, 2021
- Tiffin Roundabout (Park Road / Highway 6, STP-A-006-7(90)--22-52) engineer · Mar 2, 2021 – May 3, 2022
- Wastewater Treatment Plant Expansion – Phase Two engineer · Jan 19, 2021
- Original Town Urbanization – Phase Two engineer · Jan 19, 2021 – Jun 20, 2023
- Original Town Urbanization engineer · Jul 5, 2017
- Trails and sidewalks engineer · Mar 8, 2016 – Sep 5, 2017
- Traffic Signal engineer · Nov 25, 2015 – Feb 7, 2017
- 2013 Capital Improvement Project engineer · Feb 12, 2014
- Jasper Avenue Watermain Extension engineer · Oct 30, 2013 – Feb 12, 2014
- City parks and recreation facilities engineer · Jan 9, 2013 – Apr 9, 2014
- Joint projects with the Clear Creek Amana school district engineer · Jan 9, 2013
- Trails Phase Four engineer · Sep 26, 2012
- Industrial Park engineer · Aug 22, 2012
- Water Main engineer · Jul 10, 2002 – Aug 22, 2012
Payments to private individuals and to city staff are never shown or counted (privacy). Figures are as read from the city's published lists, not official accounting.