PROJECT UPDATE
DEVELOPMENT ASSISTANCE – ANDREW INHELDER
NO FURTHER COMMENTS
Development Name Description
Tiffin Heights West On & Off-Site Improvements No further comments sent on 10/16/24.
Shamrock Center Lot 9 No further comments sent on 12/16/24.
Park Place City Center, Part 1, Lot 3 No further comments sent on 1/29/25.
Hunt Club Phase 4 No further comments sent on 4/9/25.
Veritas Church Expansion – Phase 2 No further comments sent on 5/15/25.
Park Place City Center, Part 4, Phase 4, Lot 22 – Firing No further comments sent on 6/24/25.
Pin
Prairie Village Part 3, Phase 4 No further comments sent on 7/11/25.
Tiffin West Phase 2 No further comments sent on 7/17/25.
UNDER CONSTRUCTION
Development Name Description
Tiffin Heights West OFF Site All offsite infrastructure is installed and has passed testing.
Tiffin Heights West ON Site Sanitary sewer is complete and is being tested. Currently
working on water main and storm sewer.
Tiffin West Phase 1 ON & OFF Site Walkthrough performed on 5/28/25. Punch list provided to
developer to be completed in 2025.
Tiffin West Phase 2 Construction has begun extending Village Dr & utilities to
west.
Village Drive Extension (By water tower) Utilities and roadway grading is under construction.
Construction began 5/22/25.
The States – Anderson Addition OPD Utilities are currently under construction.
Construction began 5/29/25.
Tiffin West – Kwik Star Construction anticipated to start 8/4/25.
AWAITING RESUBMISSION
Development Name Description
Prairie Village Commercial Part 1, Lot 2 Review comments sent 7/25/23. Awaiting resubmission.
Kimberlite North of Hwy 6 Connection City, Developer, MSA, and DOT met on 8/22/24 to discuss
steps moving forward. Developer to submit proposed
improvements for review.
Prairie West Review comments sent 11/13/24. Awaiting resubmission.
Park Place City Center, Part 3, Lot 1, EMA Review comments sent 2/24/25. Awaiting resubmission.
Storage Building
Grove Park Review comments sent 6/5/25. Awaiting resubmission.
301 Main Street Site Plan Review comments sent 6/24/25. Awaiting resubmission
Bailey Way Extension Review comments sent 7/2/25. Awaiting resubmission.
Homemaker’s Site Plan – Phase 1 Review comments sent 7/17/25. Awaiting resubmission.
IN REVIEW
Development Name Description
PROJECT UPDATE
Page 2 of 3
Sources
- revize: Engineer's Report (ssrW6cKpkpeQrTeyt3I9G2gvlT38LZ.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (M-9 - Staff Cover - Engineer's Report.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: M Reports from City Personnel
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.