staff report memo · L-2
Miron - Project Update - Tiffin Recreation Center
Page 7 of 19
Text from the PDF text layer; check the PDF for anything that matters.Design/Action Items
Accomplishments
• Bid package 2 was sent out
• Final coordination items between disciplines
• ASI-2 has been sent out. This updated bid package 1 submittals to reflect on contract drawings
Upcoming Submittals/Design Deliverables
• Preliminary pre-engineered building calculations
• Rebar and foundation shop drawings
• Aggregate pier shop drawing
• CMU rebar shop drawing
• Long lead MEP equipment submittals
Submittals
• Working together to determine importance of incoming submittals from above
Requests for Information
• 7 Total RFI’s
• 5 RFI’s this month
• 2 Pending answers
‒ 0 over due
Areas of Concern / Focus
• Staying on top of submittals that are critical to upcoming work
• Finalizing color selections of flooring with the owner
Get involved, respond with
urgency, and work as a team
to get the job done. Leverage
the strengths of each
individual and overcome
obstacles as one.
Owner Progress Report | 250120 August 2025 Miron Construction Co., Inc.
|6
Sources
- revize: Attachment (v9PaS6A2oWkWF59ibVczjSuzrOcrMO.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-2 - Miron - Project Update.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Miron - Project Update - Tiffin Recreation Center
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.