staff report memo · L-2
Miron - Project Update - Tiffin Recreation Center
Page 6 of 19
Text from the PDF text layer; check the PDF for anything that matters.Executive Summary
Overview
July and August did not see much action other than dirt settling. We did get good news that the surcharge is complete
and has been removed. Topsoil has been spread out across the soccer fields awaiting seeding in the coming week.
Bid Package #2 was bid out and all contractors have been established for the entirety of the project. Coming up in
September there will be more action on site as aggregate piers will begin and foundation work will be starting in the
last week of September.
Major Milestones / Accomplishments
• Bid Package 2 was bid on 8/5
• Surcharge is complete and removed
Upcoming Milestones
• Start of aggregate piers and foundations
Key Issues and Concerns
• Applying for utility applications to begin coordinating with utility companies
‒ Electrical (Linn County REC), coordination has begun and building transformer is at their lot
‒ Gas (MidAmercian Energy), application is being reviewed and awaiting next steps
• Coordination between bid package 1 contractors and bid package 2 contractors
Be authentic, lead with
humility, and recognize the
needs of others. Care for one
another and extend a helping
hand wherever it’s needed.
Honor our history.
Owner Progress Report | 250120 August 2025 Miron Construction Co., Inc.
|5
Sources
- revize: Attachment (v9PaS6A2oWkWF59ibVczjSuzrOcrMO.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-2 - Miron - Project Update.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Miron - Project Update - Tiffin Recreation Center
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.