staff report memo · L-2
Miron - Project Update - Tiffin Recreation Center
Page 18 of 19
Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 09/05/2025
Miron Construction Co., Inc. Data Date: 05-Sep-25
Page 5 of 6
250120-15PM 20250905
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2025 2026
Dur Dur Nov
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
1580 AAAMECH 1570, 1680 Gym Area Overhead Rough In - MEP 15 15 12-Mar-26 01-Apr-26
1390
1990 MERIT 2830, 1700 PEMB - Interior Liner Panels 15 15 12-Mar-26 01-Apr-26
2110
2410 TSF 2330, 2420 Steel - Sequence 7 Running Track Stair Intall/Detail 5 5 12-Mar-26 18-Mar-26
2400,
2430 TSF 2830
2850, 1960 Steel - Sequence 9 Mechanical Screens Install 15 15 16-Mar-26 03-Apr-26
2350
1520 PEARSON 1430, 1530 1st Floor Interior Steel Stud Framing 10 10 17-Mar-26 30-Mar-26
1360
1540 ILTENS 1300, 2010, 1st Floor Overhead Rough In - Mechanical 15 15 17-Mar-26 06-Apr-26
1360 1530
1660 PEARSON 1560 1670 2nd Floor Drywall - Hang 3 3 19-Mar-26 23-Mar-26
1530 AAAMECH 1520, 1600 1st Floor In Wall Rough In - MEP 15 15 20-Mar-26 09-Apr-26
1540
1670 PEARSON 1660 1680 2nd Floor Drywall - Tape and Sand 5 5 24-Mar-26 30-Mar-26
1680 PAINTER 1580, 1700, 2nd Floor Paint 8 8 02-Apr-26 13-Apr-26
1670, 2080,
2010 PRICEELEC 2420
1540, 2900,
1830 Permenant Power 1 1 07-Apr-26 07-Apr-26
1650
1830 OTIS 1270, 1740, Elevator Installation 15 15 08-Apr-26 28-Apr-26
2010 2120
1600 PEARSON 1530, 1610 1st Floor Drywall - Hang 10 10 10-Apr-26 23-Apr-26
1840
1700 AAAMECH 1990, 2090 2nd Floor MEP Trim Out 5 5 14-Apr-26 20-Apr-26
1680
2890 PRICEELEC 1680 1760 2nd Floor - Electrical Trim and Lights 10 10 14-Apr-26 27-Apr-26
2900 ILTENS 1680 1820 2nd Floor - Fabric Duct and Diffusers 8 8 14-Apr-26 23-Apr-26
1610 PEARSON 1600 1620 1st Floor Drywall - Tape and Sand 15 15 24-Apr-26 14-May-26
1620 YOUNGS 1610, 1630, 1st Floor Paint 8 8 15-May-26 27-May-26
1470 1730,
1630 HARGERS 1620 1720,
1640, 1st Floor Ceiling Tile - Grid 15 15 28-May-26 17-Jun-26
1740,
2870 PRICEELEC 1620, 2880,
1760 1st Floor - Electrical Trim and Lig hts 10 10 04-Jun-26 17-Jun-26
1630
2880 ILTENS 1630 1820 1st Floor - Diffusers 10 10 04-Jun-26 17-Jun-26
1640 AAAMECH 1630 1650, 1st Floor Plumbing Fixtures 5 5 18-Jun-26 24-Jun-26
2090
1650 CEILING 1640 1820 1st Floor Ceiling Tile - Drop 2 2 25-Jun-26 26-Jun-26
2090 MEP 1640, 1720, HVAC Startup 3 3 25-Jun-26 29-Jun-26
1700 1820,
1730 PHILLIPSFLR 1620, 1810,
1760 Flooring - Turf Area 10 10 30-Jun-26 14-Jul-26
2090
1740 APPLEBY 1630, 2080 Soft Goods Flooring - 1st Floor 10 10 30-Jun-26 14-Jul-26
1830,
1810 FLOORING 2090
2090 1760 Athletic Flooring - 2nd Floor 15 15 30-Jun-26 21-Jul-26
2860 PHILLIPSFLR 2090 1720 Athletic Flooring - 1st Floor 10 10 30-Jun-26 14-Jul-26
2080 GENTRADES 1620, 1760 Architectural Casework Install 15 15 08-Jul-26 28-Jul-26
1680,
1720 H2I 1740
1970, 1820, Flooring - Gym Area 30 30 15-Jul-26 25-Aug-26
1620, 1950
1820 MEP 2090,
1720, 1760, Test & Balance 9 9 26-Aug-26 08-Sep-26
1650, 1880
1880 MEP 2090,
1820 1760 Commissioning 9 9 09-Sep-26 21-Sep-26
Actual Work Please review the activities for which you are responsible and the relationships to the activities of other
Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Critical Remaining Work we receive no comments from you by 5 workings days, we will assume a lack of response to be your
Milestone agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: Attachment (v9PaS6A2oWkWF59ibVczjSuzrOcrMO.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-2 - Miron - Project Update.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Miron - Project Update - Tiffin Recreation Center
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.