Construction Schedule Update 09/05/2025
Miron Construction Co., Inc. Data Date: 05-Sep-25
Page 6 of 6
250120-15PM 20250905
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2025 2026
Dur Dur Nov
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
WEATHER CONTINGENCY 19 19 08-Oct-26 03-Nov-26
WEATHER CONTINGENCY SITE WORK BP1 0 0
CRITICAL 0 0
NON-CRITICAL 0 0
WEATHER CONTINGENCY CONSTRUCTION BP2 19 19 08-Oct-26 03-Nov-26
1890 MIRON 1770 1780 Weather Contingency Construction (Sept '25-May '26 19 Days) 19 19 08-Oct-26 03-Nov-26
CRITICAL 0 0
NON-CRITICAL 0 0
CONSTRUCTION BULLETINS 0 0
PROJECT COMPLETION 44 44 10-Sep-26 10-Nov-26
1760 MIRON 1820, 1770 Quality Control Review 10 10 10-Sep-26 23-Sep-26
1870,
1770 MIRON 1880,
1760 1890, Punchlist 10 10 24-Sep-26 07-Oct-26
1780
1780 MIRON 1890, 1790 Substantial Completion 0 0 03-Nov-26*
1770
1790 MIRON 1780 1800 Punchlist Corrections 5 5 04-Nov-26 10-Nov-26
1800 MIRON 1790 Final Completion 0 0 10-Nov-26
Actual Work Please review the activities for which you are responsible and the relationships to the activities of other
Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Critical Remaining Work we receive no comments from you by 5 workings days, we will assume a lack of response to be your
Milestone agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: Attachment (v9PaS6A2oWkWF59ibVczjSuzrOcrMO.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-2 - Miron - Project Update.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: Miron - Project Update - Tiffin Recreation Center
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.