Tiffin Recreation Center Project Update
Page 8 of 20
Text from the PDF text layer; check the PDF for anything that matters.Construction Summary
Schedule Update
Scheduled November Activities: Scheduled December Activities:
• Footings (100%) • High bay steel
• Foundation walls (100%) • PEMB roofing
• Foundation backfill (95%) • PEMB exterior metal panels
• Exterior storm piping (100%)
• Erection of pre-engineered metal building (25%)
• Underground deep electrical (100%)
• Underground plumbing (100%)
• Stoop walls (100%) and topping slabs (0%)
• Additional water main work (ASI-04) (100%)
Manpower Report
List of major subcontractors & number of employees onsite:
Total number of employees: 38
• AAA Mechanical – 4 • Price Electric – 2
• Freeman Construction - 2 • Seehase Masonry - 7
• Ilten’s – 1 • SG Construction – 10
• Miron Concrete - 8 • Schrader Excavating & Grading Co – 2
• Miron Construction Manager - 2
Delays
• Weather – See Daily Log Weather Report
‒ 1 day in November
• 11/26 – High winds, 30-40mph
Weather Delays (Construction)
Scheduled Occurred Left
12 2 10
• Materials & Labor
‒ None at this time
Deliver unmatched quality,
Key Issues / Concerns & Recommended Action Steps
create meaningful
• Coordination of openings in CMU
connections, and craft
unforgettable experiences in
everything we do. Capture
what truly matters and find
ways to inspire.
Owner Progress Report | 250120 November 2025 Miron Construction Co., Inc. | 8
Sources
- revize: Attachment (xLX16Gr6xI5cW1gULRDdFzISzoZ9D5.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-4 - Tiffin Recreation Center Monthly Report - November 2025.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-4 Tiffin Recreation Center Project Update
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.