staff report memo · L-4
Tiffin Recreation Center Project Update
Page 15 of 20
Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 11/28/2025
Miron Construction Co., Inc. Data Date: 28-Nov-25
Page 1 of 4
250120-26PM 20251128
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2025 2026
Dur Dur
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
Tiffin Community Recreation Center 309 232 12-Aug-25 A 27-Oct-26
PRECONSTRUCTION 0 0
PRECONSTRUCTION - BP1 0 0
PRECONSTRUCTION - BP2 0 0
SUBMITTALS 90 80 17-Nov-25 A 24-Mar-26
A1020 GENTRADES 1120 A1030 Casework Submittal 90 80 17-Nov-25 A 24-Mar-26
A/E REVIEW / APPROVAL 10 10 25-Mar-26 07-Apr-26
A1030 GENTRADES A1020 3100 Casework Submittal - Review 10 10 25-Mar-26 07-Apr-26
FAB / DELIVER 217 140 12-Aug-25 A 17-Jun-26
1270 OTIS 1220 1830 Elevator - Fab and Deliver 70 7 12-Aug-25 A 09-Dec-25
2980 MIRON DOOR 2970 1550, Hollow Metal Frames Fab and Deliver 45 30 30-Sep-25 A 13-Jan-26
1520,
2990 MIRON DOOR 2970 2340
2920 Hollow Metal Doors Fab and Deliver 60 50 30-Sep-25 A 10-Feb-26
3000 MIRON DOOR 2970 2920, Wood Doors & Hardware Fab and Deliver 70 36 30-Sep-25 A 21-Jan-26
3080
2290 TSF 2210 2380, Steel - Sequence 3 High Steel Fab and Deliver 50 5 03-Oct-25 A 05-Dec-25
2370
2300 TSF 2220 2380 Steel - Sequence 4 GL2 thru GL5 Fab and Deliver 73 28 03-Oct-25 A 09-Jan-26
2310 TSF 2230 2390 Steel - Sequence 5 GL5 thru GL11/Track Fab and Deliver 83 38 03-Oct-25 A 23-Jan-26
1650 MEP 1510 2010 Electrical Gear - Fab and Delivery 70 35 13-Oct-25 A 20-Jan-26
1690 MEP 1910 2850 RTU - Fab and Delivery 60 35 13-Oct-25 A 20-Jan-26
2320 TSF 2240 2400 Steel - Sequence 6 Main Stair Fab and Deliver 106 57 20-Oct-25 A 19-Feb-26
2330 TSF 2250 2410 Steel - Sequence 7 Running Track Stair Fab and Deliver 111 57 20-Oct-25 A 19-Feb-26
2340 TSF 2260 2420 Steel - Sequence 8 Running Track Railing Fab and Deliver 107 57 28-Oct-25 A 19-Feb-26
2350 TSF 2270 2430 Steel - Sequence 9 Mechanical Screen Fab and Deliver 117 72 28-Oct-25 A 12-Mar-26
2530 ZEPHYR 2500, 1840 Curtain Wall/Aluminum Entrance/Glazing Fab and Deliver (Hold 45 45 01-Dec-25 03-Feb-26
3070 RO Openings)
2510 ZEPHYR 2520, 1840 Curtain Wall/Aluminum Entrance/Glazing Fab and Deliver (Field 15 15 02-Feb-26 20-Feb-26
2500, Verif ication Openings)
3100 GENTRADES 3070
A1030 2080 Casework Fab and Delivery 50 50 08-Apr-26 17-Jun-26
SITEWORK 88 88 30-Apr-26 03-Sep-26
2120 SCHRADER 1830 1940 Rough Grade 5 5 30-Apr-26 06-May-26
1940 ALL AMERICAN 2120, 1950, Site Concrete - Curbs and Sidewalks 8 8 07-May-26 18-May-26
1840 1960
1960 SCHRADER 2430, 1870 Final Grade 5 5 19-May-26 26-May-26
1340,
1870 CULVERS 1940
1440, 1760 Landscape 10 10 27-May-26 09-Jun-26
1960
1950 LLPELL 1720, 1760 Asphalt Overlay and Parking Lot Striping 5 5 27-Aug-26 03-Sep-26
1940
CONSTRUCTION 216 207 17-Nov-25 A 22-Sep-26
Actual Work
Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other
Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your
agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: Attachment (xLX16Gr6xI5cW1gULRDdFzISzoZ9D5.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-4 - Tiffin Recreation Center Monthly Report - November 2025.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-4 Tiffin Recreation Center Project Update
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.