Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 11/28/2025
Miron Construction Co., Inc. Data Date: 28-Nov-25
Page 2 of 4
250120-26PM 20251128
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2025 2026
Dur Dur
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
1370 MERIT 1460, 2380, Erect PEMB 20 12 17-Nov-25 A 16-Dec-25
2770, 2370,
1590 MIRON CONC 2760,
2790, 1440,
2850 Form and Pour Exterior Equipment Pads 5 3 19-Nov-25 A 08-Dec-25
A1040
2790 SCHRADER 2720, 1590 Backfill and Subgrade Sequence 10 & 11 3 3 01-Dec-25 03-Dec-25
2710
2370 TSF 1370, 2390 Steel - Sequence 3 High Steel Install 11 11 08-Dec-25 22-Dec-25
2290
1450 MERIT 1370 2780, Roofing 15 15 09-Dec-25 30-Dec-25
1390
2000 SEEHASE 2820, 1470, Interior CMU Bearing Walls 5 5 09-Dec-25 15-Dec-25
1370 2380
1470 SEEHASE 2000, 1620 Interior Non-Bearing CMU Block 10 10 15-Dec-25 29-Dec-25
2820
1440 MERIT 1370 2780, Exterior Metal Panels 30 30 17-Dec-25 29-Jan-26
2520,
2380 TSF 2290, 1870,
2440 Steel - Sequence 4 Columns/Beams 8 8 12-Jan-26 21-Jan-26
1370,
2850 ILTENS 2000,
1690, 2430 RTU Setting 2 2 21-Jan-26 22-Jan-26
1590
2440 TSF 2380 2450 Steel - Sequence 4 Joist/Detailing 10 10 22-Jan-26 04-Feb-26
2460 TSF 2390 2470 Steel - Sequence 5 Beams/Channels 9 9 23-Jan-26 04-Feb-26
2470 TSF 2460 2480 Steel - Sequence 5 Detailing 4 4 28-Jan-26 02-Feb-26
2450 TSF 2440 1430, Steel - Sequence 4 Metal Decking 4 4 29-Jan-26 03-Feb-26
2390
2110 AAAMECH 1440 1990 MEP Inwall Rough In - Exterior PEMB Walls 10 10 30-Jan-26 12-Feb-26
2520 ZEPHYR 1440 2510 Curtain Wall/Aluminum Entrance/Glazing - Field Verification 1 1 30-Jan-26 30-Jan-26
2780 GENTRADES 1440, 1390, Temp Heat 10 10 30-Jan-26 12-Feb-26
1450 1430
2480 TSF 2470 2950, Steel - Sequence 5 Decking 4 4 03-Feb-26 06-Feb-26
2400
2390 TSF 2370, 2460 Steel - Sequence 5 Track Rods 2 2 04-Feb-26 05-Feb-26
2450,
1430 MIRON CONC 2310
2780, 2950, Prep/Pour/Strip 2nd Floor to GL 5 5 5 13-Feb-26 19-Feb-26
2450 1520,
2400 TSF 2320, 1840,
2410 Steel - Sequence 6 Main Stair Install/Detail 5 5 20-Feb-26 26-Feb-26
2480
1410 MIRON 1390 Preinstall - Gym Floor and Slab on Grade 0 0 20-Feb-26
2950 MIRON CONC 2480, 1980 Prep/Pour/Strip 2nd Floor Sequence 2A 3 3 20-Feb-26 24-Feb-26
1430
1980 MIRON CONC 2950 2930, Prep/Pour/Strip 2nd Floor Sequence 2B 2 2 25-Feb-26 26-Feb-26
1390
1390 MIRON CONC 1410, 1580, Prep/Pour/Strip Slab on Grade - Gym Floor (Orange) 5 5 27-Feb-26 05-Mar-26
1980, 1360,
1550 PEARSON 2780,
2980, 1970
1560, 2nd Floor Interior Steel Stud Framing 5 5 27-Feb-26 05-Mar-26
1430 2340
1570 AAAMECH 1430 1580, 2nd Floor Overhead Rough In - MEP 8 8 27-Feb-26 10-Mar-26
1560
1840 GLAZING 2530, 1940, Glazing 15 15 27-Feb-26 19-Mar-26
2510, 1600
2930 TRI CITY FP 1430
1980 1680 2nd Floor Fire Protection 15 15 27-Feb-26 19-Mar-26
1970 MIRON 1390 1720 Gym Floor Moisture Mitigation 40 40 06-Mar-26 30-Apr-26
1360 MIRON CONC 1390 1540, Prep/Pour/Strip Slab on Grade - Pink 3 3 06-Mar-26 10-Mar-26
1520,
2420 TSF 2340, 2840
1680 Steel - Sequence 8 Running Track Railing Instal 7 7 10-Mar-26 18-Mar-26
2410
Actual Work
Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other
Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your
agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: Attachment (xLX16Gr6xI5cW1gULRDdFzISzoZ9D5.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-4 - Tiffin Recreation Center Monthly Report - November 2025.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-4 Tiffin Recreation Center Project Update
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.