staff report memo · L-4
Tiffin Recreation Center Project Update
Page 6 of 20
Text from the PDF text layer; check the PDF for anything that matters.Design/Action Items
Accomplishments
• N/A
Upcoming Submittals/Design Deliverables
• Submission of fire alarm shop drawings
• Submission of fire protection shop drawings
Submittals
• 15 submittals in design team court (See attached log)
Requests for Information
• 16 Total RFI’s
• 4 RFI’s this month
• 0 Pending answers
‒ 0 over due
Areas of Concern / Focus
• ASI to reflect the width of the basketball court
Get involved, respond with
urgency, and work as a team
to get the job done. Leverage
the strengths of each
individual and overcome
obstacles as one.
Owner Progress Report | 250120 November 2025 Miron Construction Co., Inc. | 6
Sources
- revize: Attachment (xLX16Gr6xI5cW1gULRDdFzISzoZ9D5.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-4 - Tiffin Recreation Center Monthly Report - November 2025.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-4 Tiffin Recreation Center Project Update
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.