Text from the PDF text layer; check the PDF for anything that matters. Tiffin Community Recreation Center Layout Name: 250120B
Construction Schedule Update 11/28/2025
Miron Construction Co., Inc. Data Date: 28-Nov-25
Page 4 of 4
250120-26PM 20251128
Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2025 2026
Dur Dur
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct ov
2090 ILTENS 1700, 1740, HVAC Startup 3 3 26-Jun-26 30-Jun-26
1640, 1730,
1730 PHILLIPSFLR 3080
2090, 2860,
1760 Flooring - Turf Area 10 10 01-Jul-26 15-Jul-26
1620
1740 APPLEBY 2090, 2920, Soft Goods Flooring - 1st Floor 10 10 01-Jul-26 15-Jul-26
1830, 2080
1810 PHILLIPSFLR 1630
2090 1760 Athletic Flooring - 2nd Floor 15 15 01-Jul-26 22-Jul-26
2080 GENTRADES 1740, 1760 Architectural Casework Install 15 15 01-Jul-26 22-Jul-26
1680,
2860 PHILLIPSFLR 1620,
2090 1720 Athletic Flooring - 1st Floor 10 10 01-Jul-26 15-Jul-26
1720 H2I 2910, 1950, Wood Flooring - Gym Area 30 30 16-Jul-26 26-Aug-26
2860, 1820
2920 MIRON DOOR 2090,
3000, 1820 Interior Door and Harware Installation 5 5 16-Jul-26 22-Jul-26
2990,
1820 MEP 1740
2920, 1880, Test & Balance 9 9 27-Aug-26 09-Sep-26
2880, 1760
1880 MEP 2900,
1820 1760 Commissioning 9 9 10-Sep-26 22-Sep-26
WEATHER CONTINGENCY 229 227 26-Nov-25 A 20-Oct-26
WEATHER CONTINGENCY SITE WORK BP1 4 4 01-Dec-25 04-Dec-25
1750 MIRON 2040 Weather Contingency Sitework (May '25-July'25 6 Days) 4 4 01-Dec-25 04-Dec-25
CRITICAL 0 0
NON-CRITICAL 0 0
WEATHER CONTINGENCY CONSTRUCTION BP2 229 10 26-Nov-25 A 20-Oct-26
1890 MIRON 1770 1780 Weather Contingency Construction (Sept '25-Jan '26 12 Days) 10 10 07-Oct-26 20-Oct-26
CRITICAL 1 0 26-Nov-25 A 26-Nov-25 A
A1040 MIRON 1370, 11/26/25 - Weather Delay High Wind 1 0 26-Nov-25 A 26-Nov-25 A
1590
NON-CRITICAL 0 0
CONSTRUCTION BULLETINS 0 0
PROJECT COMPLETION 33 33 11-Sep-26 27-Oct-26
1760 MIRON 2870, 1770 Quality Control Review 10 10 11-Sep-26 24-Sep-26
2890,
1770 MIRON 2080,
1760 1780, Punchlist 8 8 25-Sep-26 06-Oct-26
1890
1780 MIRON 1770, 1790 Substantial Completion 0 0 20-Oct-26*
1890
1790 MIRON 1780 1800 Punchlist Corrections 5 5 21-Oct-26 27-Oct-26
1800 MIRON 1790 Final Completion 0 0 27-Oct-26
Actual Work
Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other
Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If
Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your
agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will
attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.
Sources
- revize: Attachment (xLX16Gr6xI5cW1gULRDdFzISzoZ9D5.pdf) — where it was found ↗ first seen Oct 12, 2026
- sharepoint (L-4 - Tiffin Recreation Center Monthly Report - November 2025.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: L-4 Tiffin Recreation Center Project Update
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.