Tiffin Recreation Center Project Update

Dated December 16, 2025City Council — regular meeting, December 16, 2025 20 pages

Open the PDF

Page 12 of 20

Text from the PDF text layer; check the PDF for anything that matters.
Progress Photos Elevator shaft is complete Installation of underground plumbing in locker rooms Underground electrical being installed Thickened slabs under interior CMU to the East walls poured Locker room slab on grade poured and Southeast mechanical pad poured cut Owner Progress Report | 250120 November 2025 Miron Construction Co., Inc. | 12