Tiffin Recreation Center Project Update
Page 12 of 20
Text from the PDF text layer; check the PDF for anything that matters.Progress Photos
Elevator shaft is complete Installation of underground plumbing in
locker rooms
Underground electrical being installed Thickened slabs under interior CMU
to the East walls poured
Locker room slab on grade poured and Southeast mechanical pad poured
cut
Owner Progress Report | 250120 November 2025 Miron Construction Co., Inc. | 12