Text read by OCR; check the PDF for anything that matters.Progress Estimate - Lump Sum Work Contractor's Application for Payment
Owner: City of Tiffin Owner's Project No.:
Engineer: MSA Professional Services Engineer's Project No.: 13603016
Contractor: Tricon Construction Group Contractor's Project No.:
Project: Water Treatment Plant Upgrades- City of Tiffin
Contract:
Application No.: 6R Application Period: From 01/24/26 to 02/20/26 Application Date: 02/20/26
180 Bldg 10 - Foundations (Exc&BF) $25,630.00 - - 25,630.00
181 Bldg 20 - RO Fundations (Exc&BF) $45,250.00 30,616.00 30,616.00 14,634.00
182 Bldg 20 - Aeration Tank Found (Ex&BF) $15,640.00 9,384.00 9,384.00 6,256.00
183 Bldg 30 - Foundations (Exc&BF) $37,650.00 - - 37,650.00
184 - “ 2
185 Exterior Improvements - <e -
186 Asphalt Paving (Trail) $22,130.00 22,130.00 22,130.00 -
187 Concrete Paving (Site) $130,288.00 - ~ 130,288.00
188 Chain Link Fencing $32,250.00 ; - 32,250.00
189 Seeding $6,914.00 - - 6,914.00
190 - “ =
191 Utilities - - -
192 A - 12" W to Clearwell $32,544.00 29,289.60 29,289.60 3,254.40
193 B - 8" W to Clearwell $25,663.00 20,530.40 20,530.40 5,132.60
194 C - UG Storm Sewer North $48,686.00 38,948.80 38,948.80 9,737.20
195 D - 12" W Aerator to Clearwell $18,549.00 16,694.10 16,694.10 1,854.90
196 E - 12" W Bldg 10 to Bldg 20 $8,554.00 - 4,277.00 4,277.00 4,277.00
197 G - UG Storm Sewer East $67,822.00 “ 61,039.80 61,039.80 6,782.20
198 H & J- UG Storm Sewer West/South $87,552.00 - 78,796.80 78,796.80 8,755.20
199 K - UG Storm Sewer Clearwell West $42,500.00 - - 42,500.00
200 F - UG Sanitary Manholes & Piping $165,835.00 149,251.50 149,251.50 16,583.50
201 Roof Drains $2,500.00 - - 2,500.00
202 Bldg 20 - Process Drain Manhole $8,500.00 8,500.00 8,500.00 -
203 - - -
204 Process Integration (Piping) - - -
205 Structure 10 - Existing Bldg - - -
206 Process Piping Materials $55,103.74 - - 55,103.74
207 Process Piping Labor $37,550.00 - - 37,550.00
208 Valves Materials $9,500.00 - - 9,500.00
209 Valves Labor $8,250.28 - - 8,250.28
210 Structure 20 - RO Building - - -
EJCDC® C-620 Contractor's Application for Payment
© National Society of Professional Engineers for EJCDC. All rights reserved.
00 62 76 - 7 of 10 \\FILESERVER\Shares\Projects\Active\Tiffin WTP (25-012-IA)\3-Tricon\PaymentApplications\Pay Application
Sources
- revize: Agenda packet (packet_2026-03-03_69b80a70-7c35-4dc3-b01e-966369bd0f18.pdf) — where it was found ↗ first seen Oct 12, 2026
Data last updated October 18, 2026. Built from the archive's documents; see how the data is built.