Text read by OCR; check the PDF for anything that matters.Progress Estimate - Lump Sum Work Contractor's Application for Payment
Owner: City of Tiffin Owner's Project No.:
Engineer: MSA Professional Services Engineer's Project No.: 13603016
Contractor: Tricon Construction Group Contractor's Project No.:
Project: Water Treatment Plant Upgrades - City of Tiffin
Contract:
Application No.: 6R Application Period: From 01/24/26 to 02/20/26 Application Date: 02/20/26
211 Process Piping Materials $111,340.84 - 111,340.84
212 Process Piping Labor $85,502.50 - 85,502.50
213 Valves Materials $83,000.00 29,765.00 29,765.00 53,235.00
214 Valves Labor $30,614.26 - 30,614.26
215 Structure 30 - Clearwell - -
216 Process Piping Materials $62,822.42 - 62,822.42
217 Process Piping Labor $69,588.64 - 69,588.64
218 Valves Materials $42,830.00 9,034.50 9,034.50 33,795.50
219 Valves Labor $26,450.68 - 26,450.68
220 Insulation $6,825.00 - 6,825.00
221 = -
222 Pollution Control Equipment - -
223 Vertical Turbine Pumps Materials $115,300.00 112,600.00 112,600.00 2,700.00
224 Vertical Turbine Pumps Labor $24,601.24 - 24,601.24
225 Slide Gates Materials $24, 155.00 - 24,155.00
226 Slide Gates Labor $9,001.40 - 9,001.40
227 Clearwell Leak Testing $18, 144.00 : 18,144.00
228 Lab Equipment $7,216.00 - 7,216.00
229 Filter Media Replacement Materials $49,780.00 - 49,780.00
230 Filter Media Replacement Labor $16,480.00 - 16,480.00
231 Forced Draft Aerator Materials $125,890.00 - 125,890.00
232 Forced Draft Aerator Labor $14,995.00 - 14,995.00
233 RO System Materials $1,408, 500.00 - 1,408,500.00
234 RO System Labor $203,600.00 - 203,600.00
235 Chem Sys Chlorine Fluoride Caustic $125,425.00 - 125,425.00
236 Chem Systems Labor $41,582.00 - 41,582.00
237 - -
238 * -
239 - =
240 = -
= :
241
EJCDC® C-620 Contractor's Application for Payment
© National Society of Professional Engineers for EJCDC. All rights reserved.
00 62 76 - 8 of 10 \\FILESERVER\Shares\Projects\Active\Tiffin WTP (25-012-IA)\3-Tricon\PaymentApplications\Pay Application