contract agreement · K-4

Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water Treatment Facility Upgrade Project – Motion to Approve — K.4

Open the PDF Searchable (OCR) PDF

Page 60 of 63

Text from the PDF text layer; check the PDF for anything that matters.
From: Tom Shedek <[email protected]> Sent: Tuesday, February 24, 2026 4:28 PM To: Gary Ganoe <[email protected]> Cc: Andy Knapp <[email protected]>; Andrew Larson <[email protected]> Subject: RE: Tiffin WTP Low Lift Pumps - 0915659 Gary, I have to get the monthly pay app in to Clint. Is there a value on the two LL pump motors that you can provide that I can deduct from the total $115,300 amount just to get this pay app sent in? Tom Tom Shedek, PMP | Project Manager TRICON CONSTRUCTION GROUP C: 913.238.6689 [email protected] From: Gary Ganoe <[email protected]> Sent: Tuesday, February 24, 2026 9:53 AM To: Tom Shedek <[email protected]> Cc: Andy Knapp <[email protected]>; Andrew Larson <[email protected]> Subject: RE: Tiffin WTP Low Lift Pumps - 0915659 Tom, I need to discuss this with Andrew. Unfortunately, he’s out of the o2ice today. I’ll get back to you tomorrow. 4

Sources

Attached to agenda item: K-4 Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water...

This document's details as JSON

Data last updated October 17, 2026. Built from the archive's documents; see how the data is built.