Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water Treatment Facility Upgrade Project – Motion to Approve — K.4
Page 24 of 63
Text from the PDF text layer; check the PDF for anything that matters.How is water stop to be applied at the
precast and block wall joints for
chemical containment? Should the
concrete containment be poured all
around similar to the Bldg 10 chlorine
room? Typ 3 rooms.
What is the wall
height for the
containment walls?
Same at Bldg 10 -
1'-3"?