Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water Treatment Facility Upgrade Project – Motion to Approve — K.4
Page 58 of 63
Text from the PDF text layer; check the PDF for anything that matters.Tom & Clint,
Per this exchange, we agree to issue a credit of $2,700.00.
From: Tom Shedek <[email protected]>
Sent: Wednesday, February 25, 2026 1:15 PM
To: Gary Ganoe <[email protected]>
Subject: FW: Tiffin WTP Low Lift Pumps - 0915659
Gary,
Clint’s response is below. Let me know if you agree with his math and are in agreement with his deduct.
Tom
Tom Shedek, PMP | Project Manager
TRICON CONSTRUCTION GROUP
C: 913.238.6689
[email protected]
From: Clint Wienen <[email protected]>
Sent: Wednesday, February 25, 2026 12:40 PM
To: Tom Shedek <[email protected]>
Subject: RE: Tiffin WTP Low Lift Pumps - 0915659
Tom,
I am in general agreement with Gary’s logic, but I don’t agree with the math behind it.
SDs indicates 7.6-hp at the duty point. Test results indicate 8.1-hp at the duty point. Therefore di2erence = 0.5-hp
• 0.5 hp x 760 watts/hp divided by 0.917 motor e2iciency = 414 watts/hr
• A pump will need to run approximately 15 hrs/day each day to meet demand
• Most utilities are charging $0.16-0.20 per kwh. I assume they get a discounted rate b/c of there usage so I
would assume they pay around $0.12 per kwh.
414/1000 kw x 5,475hrs x $0.12 kwh ~ $270 per year
$270 x 10 years = $2,700
2
Sources
- revize: K.4 (ilsOpCSGLeJgWrIuB4PqcWDz92CA6Y.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water...
Data last updated October 17, 2026. Built from the archive's documents; see how the data is built.