Text from the PDF text layer; check the PDF for anything that matters.1. #5x36" DOWELS @ 12" O.C.SHALL BE EPOXY GROUTED A MINIMUM OF 6" INTO THE EXISTING CAST-IN-PLACE CONCRETE WALL. THE
THICKENED SLAB SHALL REMAIN 12" THICK TO THE EXISTING CIP CONCRETE WALL.
A BOND BEAM AND BLOCKING WITH PVC TRIM SHALL BE ADDED AT THE TOP OF THE MASONRY WALL.
REFER TO DRAWINGS FOR DETAILS.