contract agreement · K-4

Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water Treatment Facility Upgrade Project – Motion to Approve — K.4

Open the PDF Searchable (OCR) PDF

Page 30 of 63

Text from the PDF text layer; check the PDF for anything that matters.
1. #5x36" DOWELS @ 12" O.C.SHALL BE EPOXY GROUTED A MINIMUM OF 6" INTO THE EXISTING CAST-IN-PLACE CONCRETE WALL. THE THICKENED SLAB SHALL REMAIN 12" THICK TO THE EXISTING CIP CONCRETE WALL. A BOND BEAM AND BLOCKING WITH PVC TRIM SHALL BE ADDED AT THE TOP OF THE MASONRY WALL. REFER TO DRAWINGS FOR DETAILS. CLINT WIENEN MSA 10-28-2025