Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water Treatment Facility Upgrade Project – Motion to Approve — K.4
Page 29 of 63
Text from the PDF text layer; check the PDF for anything that matters. ESTIM ATE
Seehase Masonry, Inc. [email protected]
1018 W 1st St +1 (563) 578-3284
Sumner, IA 50674
Tricon Construction, Inc.:Tiffin WTF Upgrades 25-23
Bill to
Tricon Construction, Inc.
Estimate details P.O. Number: RFI 011 CMU Changes
Estimate no.: 2867 Sales Rep: Nate Schmidt
Estimate date: 11/20/2025
Expiration date: 12/20/2025
# Description Qty Rate Amount
1. Material and labor to complete masonry related changes per $1,945.00
request by Tricon Construction, dated 10/29/25. Changes to
CMU walls per RFI 011.
Total $1,945.00
Expiry
12/20/2025
date
Accepted date Accepted by
to k e n =
Sources
- revize: K.4 (ilsOpCSGLeJgWrIuB4PqcWDz92CA6Y.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water...
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.