Text read by the vision model; check the PDF for anything that matters.RFI
To: Clint Wienen
MSA Professional Services
400 Ice Harbor Drive #110
Dubuque, IA 52001
Ph: (563)582-3973 Fax: (563)582-4020
RFI #: 10
Date: 10/14/2025
Job: 25-012-IA Tiffin WTP
Phone:
CC: Tom Shedek (Tricon General Construction), Andy Knapp (Tricon General Construction)
Subject: Chemical Containment Questions
Drawing: 20A101, 20M301, 20M302
Spec Section: 03 30 00
Cost Impact: TBD pending response to RFI
Schedule Impact: 0
Request:
Date Required: 10/21/2025
1. Please provide the wall height for the chemical containment walls in the RO Building.
2. Please provide details as to how water stop should be applied for the chemical containment areas in the RO Building along the precast and block walls.
Requested by: Betty Keuter
Tricon General Construction
Response:
1. By code there needs to be 110% of stored volume for containment. Wall heights we had were as follows:
Caustic Soda Room (20-104)= 18" (need 550 gallons of storage)
Chlorine Room (20-105) = 18" (need 550 gallons of storage)
Anti-Scalant Room (20-102) = 15" (need 83 gallons of storage)
The wall heights and dimensions can be adjusted as necessary for precast changes, etc. as longs as the required storage volumes are satisfied.
2. It would probably make sense to pour a 6" tall concrete curb to ensure there is not an leakage of chemical at the precast wall and CMU wall interfaces. 4" pvc waterstop would be installed in the floor slab at the concrete wall/curb interfaces. Hydrophyllic waterstop shall be installed at the vertical interfaces between the precast/CMU walls and the concrete walls. See snip below on next page for reference.
Clint Wienen
Answered by
MSA
Company
October 21, 2025
Date
Sources
- revize: K.4 (ilsOpCSGLeJgWrIuB4PqcWDz92CA6Y.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water...
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.