contract agreement · K-4
Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water Treatment Facility Upgrade Project – Motion to Approve — K.4
Page 21 of 63
Text from the PDF text layer; check the PDF for anything that matters. Southside Concrete PROPOSAL
Scott McAtee / 4195 Saint Catherine Road / Bellevue IA 52031
563.543.0464 / [email protected]
Submission Date: 10/31/2025
Project: Tiffin WTP RFI # 10
Project Address:
Date of Plans:
Submitted to:
I hereby submit specifications and estimates for:
RO BLDG - 6" containment curbs - 3 locations - RFI-010
Concrete 1 CY @ 180.00 $ 180.00
Rebar $ 50.00
Addd Water Stop $ 200.00
5 Man Hours @ 80.00 $ 400.00
15% O/P $ 124.50
TOTAL $ 954.50
NOT INCLUDED:
I propose to furnish material and labor - complete in accordance with the above specifications per bid documents.
Respectfully submitted: Scott L. McAtee
This proposal may be withdrawn by Southside Concrete if not accepted within 30 days from submission date above.
Any alterations/deviations from above specifications involving extra costs will be executed only upon written order
and will become an extra charge over and above this estimate. All agreements contingent upon strikes, accidents, or
delays beyond my control.
Acceptance of Proposal
The above prices, specifications and conditions are satisfactory and are hereby accepted. Southside is authorized to
perform work as quoted. Payments will be made per bid documents.
Signature: Date:
Sources
- revize: K.4 (ilsOpCSGLeJgWrIuB4PqcWDz92CA6Y.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water...
Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.