Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water Treatment Facility Upgrade Project – Motion to Approve — K.4
Page 2 of 63
Text read by the vision model; check the PDF for anything that matters.CHANGE ORDER NO.: 2
Owner: City of Tiffin
Engineer: MSA Professional Services
Contractor: Tricon Construction Group
Project: Tiffin WTF Upgrade
Contract Name: 13603021 – Tiffin WTF Upgrade
Date Issued: April 1, 2026
Owner’s Project No.:
Engineer’s Project No.: 13603021
Contractor’s Project No.: 25-012-IA
Effective Date of Change Order: April 7, 2026
The Contract is modified as follows upon execution of this Change Order:
Description: This change order shall incorporate the following changes:
• Increase for new water service = $3,454.10
• Increase for installation of bollards and concrete pad at transformer location b/c of relocation = $1,804.21
• Increase to include concrete curbs for chemical containment areas = $1,022.01
• Increase to change masonry wall in existing WTP to load bearing to support truss loadings = $2,556.62
• Decrease to eliminate (2) 6” and (1) 8” butterfly valves on the clean in place piping and to include (1) 12” butterfly valve in the forced draft aerator vault = ($1,619.74)
• Increase to include ductwork intake in the MCC Room = $3,402.31
• Decrease for acceptance of low lift pumps which had a lower efficiency than specified = ($2,809.94)
Attachments: Change order request documents.
<table>
<tr>
<th colspan="2">Change in Contract Price</th>
<th colspan="2">Change in Contract Times</th>
</tr>
<tr>
<td>Original Contract Price:</td>
<td>$ 12,182,553.00</td>
<td>Original Contract Times:</td>
<td>Substantial Completion: 9/30/26<br>Ready for final payment: 11/30/26</td>
</tr>
<tr>
<td colspan="2"><b>Increase from previously approved Change Orders No. 1 to No. 1</b></td>
<td colspan="2"><b>[Increase] [Decrease] from previously approved Change Orders No.1 to No. [Number of previous Change Order]:</b><br>Substantial Completion: N/A<br>Ready for final payment: N/A</td>
</tr>
<tr>
<td>Contract Price prior to this Change Order:</td>
<td>$ 12,194,973.34</td>
<td>Contract Times prior to this Change Order:</td>
<td>Substantial Completion: 9/30/26<br>Ready for final payment: 11/30/26</td>
</tr>
<tr>
<td><b>Increase</b> this Change Order:</td>
<td>$ 7,728.57</td>
<td><b>[Increase] [Decrease]</b> this Change Order: $0.00</td>
<td>Substantial Completion: 0<br>Ready for final payment: 0</td>
</tr>
<tr>
<td>Contract Price incorporating this Change Order:</td>
<td>$ 12,202,701.91</td>
<td>Contract Times with all approved Change Orders:</td>
<td>Substantial Completion: 9/30/26<br>Ready for final payment: 11/30/26</td>
</tr>
</table>
Recommended by Engineer
By: [signature]
Title: Senior Project Engineer
Date: April 2, 2026
Accepted by Contractor
[signature]
Owner
04.02.26
Sources
- revize: K.4 (ilsOpCSGLeJgWrIuB4PqcWDz92CA6Y.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Discussion and Consideration of Change Order #2 – Tricon Construction – Tiffin Water...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.