contract agreement · K-4
Discussion and Consideration of Change Order #15 – Boomerang Corporation – North Park Road Improvements Project – Motion to Approve — K.4
Page 2 of 5
Text from the PDF text layer; check the PDF for anything that matters. City of Tiffin - Iowa
Change Order Details
52-7662-615
Description STP-U-7662(615)--70-52, Letting Date- December 17, 2024
Prime Contractor Boomerang Corp.
13225 Circle Dr Suite A, Anamosa, IA 52205
Anamosa, IA, IA 52205
Change Order 15
Status Pending
Date Created 04/23/2026
Type Non-Substantial
Summary Add item for temporary pipe for flow conveyance into 72in culvert for temporary flow conveyance during S-06 installation.
Change Order Description 8220: Add item for 2503-0111018 STORM SEWER GRAVITY MAIN, TRENCHED, HIGH DENSITY POLYETHYLENE PIPE (HDPE), 18
IN.
Awarded Project Amount $5,458,891.91
Authorized Project Amount $5,554,449.41
Change Order Amount $1,250.00
Revised Project Amount $5,555,699.41
B-Reason for Change
8220: Add 20 LF of 18IN HDPE temporary pipe from approx. STA 222+67 to STA 222+47. This temporary pipe is intended to tie into the detention basin outlet outside of the
ROW which is the primary flow inlet into the North Park Road storm system, the temporary 18in pipe will be outlet into the new 72in culvert which is already installed to send
flows into the new system while construction of the structure S-06 (cast-in-place) takes place (the 72in culvert outlets from S-06).
Change Order Details: 04/24/2026
52-7662-615 Page 1 of 3
Sources
- revize: K.4 (Et92sVw4SNm9ZmWnFH0prXVSscU83u.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Discussion and Consideration of Change Order #15 – Boomerang Corporation – North Park...