contract agreement · K-4
Discussion and Consideration of Change Order #15 – Boomerang Corporation – North Park Road Improvements Project – Motion to Approve — K.4
Page 3 of 5
Text from the PDF text layer; check the PDF for anything that matters. C-Settlement for cost(s) of change
8220: Agreed unit price.
D-Justification for cost(s)
8220: Unit price ($62.50/LF) is below the average unit bid price of the same item ($69.00/LF) and also below the maximum unit bid price ($400.00/LF) when compared with a Bid
Tab analysis of bid prices for the item from December 2024 to April 2026. Unit price DOES NOT include Prime Contractor markup of 10% per 1109.03,3.
E-contract time adjustment
None. This change has no impact on the controlling item of work.
New Items
Line Number Item ID Unit Quantity Unit Price Extension
Section: 0001 - STP-U-7662(615)--70-52, ROADWAY ITEMS
8220 2503-0111018 LF 20.000 $62.500 $1,250.00
STORM SEWER GRAVITY MAIN, TRENCHED, HIGH DENSITY POLYETHYLENE PIPE (HDPE), 18 IN.
Funding Details
52-7662-615-CAT-3 NON-PARTICIPATING 20.000 $62.500 $1,250.00
1 item Total: $1,250.00
Funding Summary
Fund Package Original Amount Authorized Amount Pending Change Revised Amount
52-7662-615-CAT-1 ROADWAY ITEMS $4,872,701.91 $4,866,768.26 $0.00 $4,866,768.26
Change Order Details: 04/24/2026
52-7662-615 Page 2 of 3
Sources
- revize: K.4 (Et92sVw4SNm9ZmWnFH0prXVSscU83u.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Discussion and Consideration of Change Order #15 – Boomerang Corporation – North Park...
Data last updated October 15, 2026. Built from the archive's documents; see how the data is built.