contract agreement · K-4
Discussion and Consideration of Change Order #15 – Boomerang Corporation – North Park Road Improvements Project – Motion to Approve — K.4
Page 1 of 5
Text from the PDF text layer; check the PDF for anything that matters. AGENDA ITEM # K-4
AGENDA INFORMATION
TIFFIN CITY COUNCIL COMMUNICATION
DATE: May 1, 2026
AGENDA ITEM: Discussion and Consideration of Change Order #15 – Boomerang
Corporation – North Park Road Improvements Project
ACTION: Motion
Background
The City entered into a construction contract with Boomerang Corporation for the North Park
Road Improvements project following the December 17, 2024, letting. The project includes
roadway, storm sewer, and associated infrastructure improvements.
During construction sequencing for Structure S-06 (cast-in-place), a need was identified to
temporarily convey stormwater flows from an upstream detention basin into the newly installed
72-inch culvert to maintain system functionality and prevent backup during construction
activities.
Change Order No. 15 is a non-substantial change order that adds a temporary storm sewer pipe
to maintain flow conveyance during construction of Structure S-06. The change is necessary to
safely manage stormwater flows while work continues and does not impact the project schedule.
Change Order No. 15 adds the following new item of work 20 linear feet of 18-inch HDPE storm
sewer pipe to provide temporary flow conveyance from approximately Station 222+67 to Station
222+47.
This temporary pipe ties the detention basin outlet located outside of the right-of-way into the
new 72-inch culvert, allowing stormwater to bypass the S-06 construction area until permanent
work is completed.
Change Order Details:
• Change Order Number: 15
• Type: Non-Substantial
• Change Order Amount: $1,250.00
• Unit Price: $62.50 per linear foot
• Contract Time Impact: None
The unit price is below the average bid price ($69.00/LF) and well below the maximum bid price
identified in the bid analysis. No contractor markup is included.
Staff Recommendation
Staff recommends approval of Change Order No. 15 to the North Park Road Improvements
project contract with Boomerang Corporation in the amount of $1,250.00, increasing the total
contract amount to $5,555,699.41.
ATTACHMENTS: Change Order
1
Sources
- revize: K.4 (Et92sVw4SNm9ZmWnFH0prXVSscU83u.pdf) — where it was found ↗ first seen Oct 12, 2026
Attached to agenda item: K-4 Discussion and Consideration of Change Order #15 – Boomerang Corporation – North Park...