staff report memo · L-3
Tiffin Recreation Center Monthly Report — L.3
Page 12 of 18
Text from the PDF text layer; check the PDF for anything that matters.Progress Photos
2nd Floor stud installation 2nd Floor in wall rough-ins and blocking
Locker room stud wall installation
Locker room above ceiling MEP
installation
Locker room drywall installation Mechanical room drywall installation
Owner Progress Report | 250120 April 2026 Miron Construction Co., Inc. | 12