Tiffin Recreation Center Monthly Report — L.3

Open the PDF

Page 13 of 18

Text from the PDF text layer; check the PDF for anything that matters.
Progress Photos Mechanical room drywall installation Top track installation on North side Gym floor poured and being finished Ductwork & Fire Protection installation on North side Track for divider curtain installed Ductwork being installed in lobby ceiling Owner Progress Report | 250120 April 2026 Miron Construction Co., Inc. | 13