Tiffin Recreation Center Monthly Report — L.3

Open the PDF

Page 16 of 18

Text from the PDF text layer; check the PDF for anything that matters.
Tiffin Community Recreation Center Layout Name: 250120B Construction Schedule Update 05/08/2026 Miron Construction Co., Inc. Data Date: 08-May-26 Page 1 of 3 250120-48PM 20260508 Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2026 Dur Dur Nov May Jun Jul Aug Sep Oct Tiffin Community Recreation Center 195 120 30-Jan-26 A 28-Oct-26 PRECONSTRUCTION 0 0 PRECONSTRUCTION - BP1 0 0 PRECONSTRUCTION - BP2 0 0 SUBMITTALS 0 0 A/E REVIEW / APPROVAL 0 0 FAB / DELIVER 115 40 30-Jan-26 A 07-Jul-26 3000 MIRON DOOR 2970 2920, Wood Doors & Hardware Fab and Deliver 70 14 30-Jan-26 A 29-May-26 3080 1270 OTIS 1220 1830 Elevator - Fab and Deliver 43 25 06-Apr-26 A 15-Jun-26 3220 H2I 3210 2910 Gym Equipment Procurement 45 30 17-Apr-26 A 22-Jun-26 3100 GENTRADES A1080, 2080 Casework Fab and Delivery 50 40 27-Apr-26 A 07-Jul-26 A1030 SITEWORK 57 57 08-Jul-26 25-Sep-26 2120 SCHRADER 1830 1940 Rough Grade 5 5 08-Jul-26 14-Jul-26 1940 ALL AMERICAN 2120, 1950, Site Concrete - Curbs and Sidewalks 8 8 15-Jul-26 24-Jul-26 1840 1960 1960 SCHRADER 2430, 1870 Final Grade 5 5 27-Jul-26 31-Jul-26 1340, 1870 CULVERS 1940 1440, 1760 Landscape 10 10 03-Aug-26 14-Aug-26 1960 1950 LLPELL 1940 1760 Asphalt Overlay and Parking Lot Striping 5 5 21-Sep-26 25-Sep-26 CONSTRUCTION 135 105 30-Mar-26 A 07-Oct-26 1520 PEARSON 3230, 1530, 1st Floor Interior Steel Stud Framing 13 1 30-Mar-26 A 11-May-26 2980, 3150, 1540 ILTENS 1430 3230, 3150, 1620 1st Floor Overhead Rough In - Mechanical 15 3 08-Apr-26 A 13-May-26 1300, 1970 MIRON 2850 1390 1720 Gym Floor Moisture Mitigation 40 17 08-Apr-26 A 03-Jun-26 3150 PRICEELEC 1520, 3260, 1st Floor In Wall Rough In - Electrical 18 2 09-Apr-26 A 12-May-26 1520 3280, 2930 TRI CITY FP 1980 3290 1680, 2nd Floor Fire Protection 5 1 13-Apr-26 A 11-May-26 2940 1600 PEARSON 3280, 3370 1st Floor Drywall South - Top Out 30 1 17-Apr-26 A 13-May-26 1520 2940 TRI CITY FP 3230, 3340 1st Floor Fire Protection 15 10 27-Apr-26 A 26-May-26 2840, 1990 MERIT 2930 3140, 2890 PEMB - Interior Liner Panels 15 8 29-Apr-26 A 20-May-26 2110, 1840 GLAZING 2830 2530, 1940 Glazing 15 15 11-May-26 01-Jun-26 2510, 3180 ILTENS 1430 1390 1680 Gym Area Overhead Rough In - Mechanical 10 10 11-May-26 22-May-26 1660 PEARSON 3160, 1670, 2nd Floor Drywall - Hang 3 3 12-May-26 14-May-26 1560, 3360, 3170 PRICEELEC 3300 1390, 3370 1680 Gym Area Overhead Rough In - Electrical 15 15 12-May-26 02-Jun-26 3160 3310 PEARSON 1520 3380, 1st Floor Furred Out Walls - Studs 8 8 12-May-26 21-May-26 3380 3260 PRICEELEC 3150 3270 1st Floor Overhead Rough In - Electrical 15 15 13-May-26 03-Jun-26 Actual Work Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.

Sources

Attached to agenda item: L-3 Tiffin Recreation Center Monthly Report

This document's details as JSON

Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.