Tiffin Recreation Center Monthly Report — L.3

Open the PDF

Page 17 of 18

Text from the PDF text layer; check the PDF for anything that matters.
Tiffin Community Recreation Center Layout Name: 250120B Construction Schedule Update 05/08/2026 Miron Construction Co., Inc. Data Date: 08-May-26 Page 2 of 3 250120-48PM 20260508 Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2026 Dur Dur Nov May Jun Jul Aug Sep Oct 1670 PEARSON 1660 3320 2nd Floor Drywall - Tape and Sand 5 5 15-May-26 21-May-26 3360 PEARSON 1660, 3390, 1st Floor North Drywall Hang 5 5 15-May-26 21-May-26 2340 3390 3370 PEARSON 1660, 3380, 1st Floor South Drywall Hang 8 8 15-May-26 27-May-26 1600 3380 3380 PEARSON 3370, 1620, 1st Floor South Drywall - Tape and Finish 8 8 19-May-26 29-May-26 3370, 1620 3390 PEARSON 3310, 3360, 3330 1st Floor North Drywall - Tape and Finish 10 10 19-May-26 02-Jun-26 3360 1620 YOUNGS 1540, 3020, 1st Floor Paint - Shower and Locker Room 15 15 22-May-26 12-Jun-26 1470, 2870, 3320 YOUNGS 3380, 1670 2080, 3010 Paint - 2nd Floor Restroom Core 3 3 22-May-26 27-May-26 3010 APPLEBY 3320 1700 2nd Floor Wall Tile 8 8 28-May-26 08-Jun-26 3020 APPLEBY 1620 1640 1st Floor Wall Tile 15 15 28-May-26 17-Jun-26 1680 YOUNGS 3180, 2910, 2nd Floor Al Overhead/Gym/U nder Track Paint 20 20 03-Jun-26 30-Jun-26 3170, 2890, 3270 PRICEELEC 2930, 3260 2900, 2010, 1st Floor Wire Pull 5 5 04-Jun-26 10-Jun-26 2870 2010 PRICEELEC 3270, 1830 Permenant Power 1 1 11-Jun-26 11-Jun-26 1650 1700 AAAMECH 3010 1770 2nd Floor Plumbing Fixtures 5 5 12-Jun-26 18-Jun-26 3080 MIRON DOOR 3000, 2090 Door and Hardware Installation 8 8 15-Jun-26 24-Jun-26 1620 3340 YOUNGS 1620, 3330, 1st Floor Ceiling Paint 10 10 15-Jun-26 26-Jun-26 2940 1630 1830 OTIS 2010, 2120, Elevator Installation 15 15 16-Jun-26 07-Jul-26 1270 1740 3330 YOUNGS 3340, 1630 1st Floor Paint - North 10 10 29-Jun-26 13-Jul-26 3390 2890 PRICEELEC 1990, 1760 2nd Floor - Electrical Trim and Lights 10 10 01-Jul-26 15-Jul-26 1680 2900 ILTENS 1680 1820 2nd Floor - Fabric Duct and Diffusers 8 8 01-Jul-26 13-Jul-26 2910 H2I 3220, 1720 Gym Equipment - Installation 20 20 01-Jul-26 29-Jul-26 1680 3350 YOUNGS 1680 1720 Paint - Stairs and Handrail 10 10 01-Jul-26 15-Jul-26 1630 HARGERS 3340, 1650, 1st Floor Ceiling Tile - Grid 15 15 14-Jul-26 03-Aug-26 3330 2870, 2870 PRICEELEC 1630, 2880, 1650, 1st Floor - Electrical Trim and Lig hts 10 10 21-Jul-26 03-Aug-26 1620, 1760 2880 ILTENS 3270 1630 2090, 1st Floor - Diffusers 5 5 21-Jul-26 27-Jul-26 1820 2090 ILTENS 2880, 1740, HVAC Startup 3 3 28-Jul-26 30-Jul-26 3080 1730, 1720 H2I 2910, 2860, 1820, Wood Flooring - Gym Area 30 30 31-Jul-26 11-Sep-26 2090, 2860 1730 PHILLIPSFLR 1970, 3240, 1760 Flooring - Turf Area 10 10 31-Jul-26 13-Aug-26 2090 1810 PHILLIPSFLR 2090 1760, Athletic Flooring - 2nd Floor 15 15 31-Jul-26 20-Aug-26 2860 1650 CEILING 2870, 1820 1st Floor Ceiling Tile - Drop 2 2 04-Aug-26 05-Aug-26 1630 1740 APPLEBY 2090, 2920, Soft Goods Flooring - 1st Floor 10 10 04-Aug-26 17-Aug-26 1830, 2080 2080 GENTRADES 1630 1740, 1760, Architectural Casework Install 15 15 04-Aug-26 24-Aug-26 1620, 1640 3250 TRI CITY FP 3100 1630 1760 Fire Protection - Trim Out Heads 4 4 04-Aug-26 07-Aug-26 Actual Work Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.

Sources

Attached to agenda item: L-3 Tiffin Recreation Center Monthly Report

This document's details as JSON

Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.