Tiffin Recreation Center Monthly Report — L.3

Open the PDF

Page 18 of 18

Text from the PDF text layer; check the PDF for anything that matters.
Tiffin Community Recreation Center Layout Name: 250120B Construction Schedule Update 05/08/2026 Miron Construction Co., Inc. Data Date: 08-May-26 Page 3 of 3 250120-48PM 20260508 Activity ID Resp PredecessorsSuccessors Activity Name Orig Rem Start Finish 2026 Dur Dur Nov May Jun Jul Aug Sep Oct 2920 MIRON DOOR 3000, 1820 Interior Door and Harware Installation 5 5 18-Aug-26 24-Aug-26 2990, 1640 AAAMECH 1740 3020, 1770 1st Floor Plumbing Fixtures 5 5 25-Aug-26 31-Aug-26 2080 1820 MEP 2920, 1880 Test & Balance 9 9 14-Sep-26 24-Sep-26 2880, 2860 PHILLIPSFLR 2900, 2090, 1760 Athletic Flooring - 1st Floor 10 10 14-Sep-26 25-Sep-26 1810, 1880 MEP 1720 1820 1770 Commissioning 9 9 25-Sep-26 07-Oct-26 WEATHER CONTINGENCY 0 0 11-May-26 11-May-26 WEATHER CONTINGENCY SITE WORK BP1 0 0 11-May-26 11-May-26 1750 MIRON 2040 Weather Contingency Sitework (May '25-July'25 6 Days) 0 0 11-May-26 11-May-26 CRITICAL 0 0 NON-CRITICAL 0 0 WEATHER CONTINGENCY CONSTRUCTION BP2 0 0 CRITICAL 0 0 NON-CRITICAL 0 0 CONSTRUCTION BULLETINS 0 0 PROJECT COMPLETION 23 23 28-Sep-26 28-Oct-26 1760 MIRON 2870, 1770 Quality Control Review 10 10 28-Sep-26 09-Oct-26 2890, 1770 MIRON 2080, 1880, 1780, Punchlist 8 8 12-Oct-26 21-Oct-26 1760, 1890 1780 MIRON 1700, 1770, 1790 Substantial Completion 0 0 21-Oct-26* 1890 1790 MIRON 1780 1800 Punchlist Corrections 5 5 22-Oct-26 28-Oct-26 1800 MIRON 1790 Final Completion 0 0 28-Oct-26 Actual Work Remaining Work Please review the activities for which you are responsible and the relationships to the activities of other Critical Remaining Work trades. If you have questions or comments, please contact Patrick Myers & Corey Boyles immediately. If Milestone we receive no comments from you by 5 workings days, we will assume a lack of response to be your agreement and commitment to the durations, relationships, and sequencing of this plan. As always, we will attempt to improve upon the dates shown. Periodic updates will be distributed as the project progresses.

Sources

Attached to agenda item: L-3 Tiffin Recreation Center Monthly Report

This document's details as JSON

Data last updated October 16, 2026. Built from the archive's documents; see how the data is built.